Quick answers
What is this project?
PROPOSED 60 KLPD CAPACITY CANE JUICE AND B-HEAVY MOLASSES BASED DISTILLERY AND 1.5 MW CAPTIVE POWER PLANT by M/S. M.R.KRISHNAMURTHY CO-OPERATIVE SUGAR MILLS LTD. (MRKCSML) is an approved industrial project in Settiyatope (Tp), Bhuvanagiri, Cuddalore, Tamil Nadu. The site covers 17.1 acres.
Who is building it?
The applicant is Krishnamurthy Cooperative Sugar Mills LTD.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 10 May 2023), as of 27 Nov 2026.
Where is it?
In Settiyatope (Tp), Bhuvanagiri, Cuddalore, Tamil Nadu.
How big is it?
It has a stated cost of ₹85 crore and a site of 17.1 acres.
When was it filed?
The application was filed on 10 May 2023.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 10 May 2023 |
| Application filed | 10 May 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Krishnamurthy Cooperative Sugar Mills LTD |
| Land area | 17.1 acres (6.9 ha) |
| Project cost | ₹85 crore |
| Village / locality | Settiyatope (Tp) |
| Taluk / tehsil | Bhuvanagiri |
| District | Cuddalore |
| State | Tamil Nadu |
| Location from | Site boundary on record |
| Our reference | WID-TN-01099 |
In context
23 applications in Cuddalore since January 2022 are in the same category (Industry): 14 approved, 8 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 42 days from filing to approval. At 17.1 acres, this one is smaller than 57% of them.
Where it is
Settiyatope (Tp), Bhuvanagiri, Cuddalore, Tamil Nadu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Koodalaiyathur Village Sand Quarry (16.00.0 Ha) — lapsed, 9.9 km away
- Silica Sand Quarry Project Belongs to Thiru. S. Sundar — environmental approval granted, 17.3 km away
- Expansion of 2x660MW Super Critical Lignite based Thermal Power Project by NLC… — returned to applicant, 18.3 km away
- Neyveli New Thermal Power Station (2x500 MW) — environmental approval granted, 18.6 km away
- C.Thirugnanasammanthamoorthy, Earth Quarry Extent of 1.19.5Ha S.F.Nos. 133/4E,… — environmental approval granted, 19.3 km away
- Thiru. R. Thamodharan Earth Quarry — environmental approval granted, 19.7 km away
- KOTHATTAI VILLAGE, Earth Quarry Project Belongs to M/s. SRI VENKATACHALAPATHY… — environmental approval granted, 21 km away