One of 2 filings for this project. The project's main page, with every filing and where each stands: Building project by OLA Electric Technologies Private Limited
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 30 Sept 2025 |
| Application filed | 8 Sept 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Buildings & townships |
| Applicant | Ola Electric Technologies Private Limited |
| Use | Industrial |
| Land area | 135 acres (54.6 ha) |
| Project cost | ₹1,526.3 crore |
| Village / locality | Balethottam |
| Taluk / tehsil | Pochampalli |
| District | Krishnagiri |
| State | Tamil Nadu |
| Location from | Site boundary on record |
| Our reference | WID-TN-03012 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 3 Feb 2026 | Environmental approval granted | 135 acres | ₹1,526.3 crore |
| Early planning filed 8 Sept 2025 (this page) | Cleared for impact study | 135 acres | ₹1,526.3 crore |
In context
78 applications in Krishnagiri since January 2022 are in the same category (Buildings & townships): 53 approved, 18 filed or under review, and 7 withdrawn, lapsed or rejected. The approved ones took a median of 40 days from filing to approval. At 135 acres, this one is larger than 83% of them.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Balethottam, Pochampalli, Krishnagiri, Tamil Nadu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Building project by OLA Electric Technologies Private Limited — environmental approval granted, 0 m away
- Proposed Expansion of Existing Special Economic Zone in Bargur Sipcot… — cleared for impact study, 650 m away
- Integrated Common Hazardous Waste Treatment, Storage & Disposal Facility by… — environmental approval granted, 900 m away
- Proposed Manufacturing of API & API Intermediates — environmental approval granted, 1 km away
- Proposed Manufacturing of Dyes and Dye Intermediates Facility — environmental approval granted, 1.3 km away
- Proposed Manufacturing of Dyes and Dye Intermediates Facility — cleared for impact study, 1.3 km away
- Building project by M/s. OLA CELL TECHNOLOGIES PRIVATE LIMITED — environmental approval granted, 1.4 km away
- Building project by M/s. OLA CELL TECHNOLOGIES PRIVATE LIMITED — environmental approval granted, 1.4 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.