Application for No Increase in Pollution Load is a proposed project in Kanadukandan, Virudhachalam, Cuddalore, Tamil Nadu. The site covers 50.8 acres.
Who is building it?
The applicant is Shree Ambika Sugars Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Kanadukandan, Virudhachalam, Cuddalore, Tamil Nadu.
How big is it?
It has a stated cost of ₹75 crore and a site of 50.8 acres.
When was it filed?
The application was filed on 8 Dec 2025.
Project details
| Status | Initial checks |
|---|---|
| Status since | 8 Dec 2025 |
| Application filed | 8 Dec 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Other |
| Applicant | Shree Ambika Sugars Limited |
| Land area | 50.8 acres (20.5 ha) |
| Project cost | ₹75 crore |
| Village / locality | Kanadukandan |
| Taluk / tehsil | Virudhachalam |
| District | Cuddalore |
| State | Tamil Nadu |
| Location from | Site boundary on record |
| Our reference | WID-TN-03628 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 8 Dec 2025 (this page) | Initial checks | 50.8 acres | ₹75 crore |
| New project filed 17 Nov 2025 | Initial checks | 50.8 acres | ₹75 crore |
In context
10 applications in Cuddalore since January 2022 are in the same category (Other): 3 approved, 4 filed or under review, and 3 withdrawn, lapsed or rejected.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kanadukandan, Virudhachalam, Cuddalore, Tamil Nadu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Application for Change of Name in Environmental Clearance — more information requested, 0 m away
- Application for No Increase in Pollution Load — initial checks, 0 m away
- Laying of Aerial OFC along the Reserve Forests of Cuddalore District — lapsed, 1.9 km away
- Laying of Aerial OFC along the Reserve Forests of Cuddalore District — lapsed, 1.9 km away
- Laying of OFC through TNEB poles (Existing-26 no's), in the Reserve Forest of… — more information requested, 4.8 km away
- Expansion of 2x660MW Super Critical Lignite based Thermal Power Project by NLC… — returned to applicant, 6.4 km away
- Neyveli New Thermal Power Station (2x500 MW) — environmental approval granted, 11.4 km away
- M. Ramakrishnan, Gravel and Pebbles Quarry Project — environmental approval granted, 11.4 km away