Project details
| Official title | Proposed Construction of Industrial Building (Light and Heavy Engineering/ Manufacturing/Assembling Park/ Industrial Storage) |
|---|---|
| Status | Environmental approval granted |
| Status since | 16 Nov 2026 |
| Application filed | 16 Sept 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Neelimalaa Land Promoters LLP |
| Use | Industrial |
| Towers | 3 |
| Height | 17 m |
| Land area | 16.5 acres (6.7 ha) |
| Built-up area | 40,000 m² (4,30,556 sq ft) |
| Plot area | 66,596 m² (7,16,833 sq ft) |
| Project cost | ₹104.1 crore |
| Village / locality | Singadivakkam |
| Taluk / tehsil | Kancheepuram |
| District | Kanchipuram |
| State | Tamil Nadu |
| Location from | Site boundary on record |
| Our reference | WID-TN-04707 |
In context
219 applications in Kanchipuram since January 2022 are in the same category (Buildings & townships): 151 approved, 45 filed or under review, and 23 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 16.5 acres, this one is smaller than 54% of them.
20 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Singadivakkam, Kancheepuram, Kanchipuram, Tamil Nadu. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Synthetic Organic Chemicals — environmental approval granted, 350 m away
- Ordinary Earth Quarry of Mr.P.Puvithrajan — environmental approval granted, 700 m away
- Singadivakkam Village Ordinary Earth Mining Project — withdrawn, 700 m away
- Proposed Expansion of the Industrial Building by M/s. Fritzmeier Motherson… — environmental approval granted, 1.4 km away
- Proposed Expansion of the Industrial Building by M/s. Fritzmeier Motherson… — withdrawn, 1.4 km away
- Proposed expansion of Industrial Buildings — environmental approval granted, 2.4 km away
- Proposed Ordinary Earth Quarry of Thiru. K. Gowri Shankar — environmental approval granted, 2.8 km away
- Motherson Electronic Components Company — more information requested, 3 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.