Quick answers
What is this project?
Building stone (Sandstone) mine (Gata No. 360, Lease area-1.01 Ha.) for the production capacity 10100 m3, Village- Adhwar, Tehsil- Chunar, District- Mirzapur Uttar Pradesh by Shri Arjun Singh is an approved mining project in Lalpur, Chunar, Mirzapur, Uttar Pradesh. The site covers 2.5 acres.
Who is building it?
The applicant is Arjun Singh.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 15 Nov 2022), as of 27 Nov 2026.
Where is it?
In Lalpur, Chunar, Mirzapur, Uttar Pradesh.
How big is it?
It has a stated cost of ₹71 lakh and a site of 2.5 acres.
When was it filed?
The application was filed on 15 Nov 2022.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 15 Nov 2022 |
| Application filed | 15 Nov 2022 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Arjun Singh |
| Land area | 2.5 acres (1 ha) |
| Project cost | ₹71 lakh |
| Village / locality | Lalpur |
| Taluk / tehsil | Chunar |
| District | Mirzapur |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-00110 |
In context
404 applications in Mirzapur since January 2022 are in the same category (Mining): 312 approved, 49 filed or under review, and 43 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 2.5 acres, this one is smaller than 75% of them.
11 other mining leases have applied within 500 m of this site; together with this one they cover 45.2 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 87 mining leases have applied within 5 km.
Where it is
Lalpur, Chunar, Mirzapur, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Existing Project of "Building Stone Sandstone Mining Project" at Gata No. 360… — returned to applicant, 100 m away
- "Building stone, Sand Stone, Quartizite, Ballast, Gitti" Mine from Village-… — cleared for impact study, 200 m away
- Proposed Adhwar Building Stone (Sandstone) Mining Project — environmental approval granted, 200 m away
- Proposed Adhwar Building Stone (Sandstone) Mining Project — more information requested, 200 m away
- Proposed project of Building Stone Sand Stone Quartizite Ballast (Gitti)… — under environmental review, 200 m away
- Proposed project of Building Stone Sand Stone Quartizite Ballast (Gitti)… — under environmental review, 350 m away
- Proposed Bhagautidei Building Stone (Sandstone) Mining Project At Arazi No… — environmental approval granted, 350 m away
- Building Stone Sandstone, Gitti , Boulder, Patiya Mine at Arazi No 519… — environmental approval granted, 400 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.