What is this project?
Environment Clearance of proposed "Upgradation and renovation of District Jail Complex" at Bareilly, Uttar Pradesh is an approved building project in Bareily (Municipal Area), Bareilly, Uttar Pradesh. The site covers 71.2 acres.
Who is building it?
The applicant is Sanjeev Kumar.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 2 Apr 2023), as of 27 Nov 2026.
Where is it?
In Bareily (Municipal Area), Bareilly, Uttar Pradesh.
How big is it?
It has a stated cost of ₹1.7 crore and a site of 71.2 acres.
When was it filed?
The application was filed on 2 Apr 2023.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 2 Apr 2023 |
| Application filed | 2 Apr 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Sanjeev Kumar |
| Land area | 71.2 acres (28.8 ha) |
| Project cost | ₹1.7 crore |
| Village / locality | Bareily (Municipal Area) |
| Taluk / tehsil | Bareilly |
| District | Bareilly |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-00852 |
In context
14 applications in Bareilly since January 2022 are in the same category (Buildings & townships): 8 approved, 3 filed or under review, and 3 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 71.2 acres, this one is larger than 64% of them.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bareily (Municipal Area), Bareilly, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Residential Plotted Development and Commercial Development at Chaupla… — initial checks, 650 m away
- Proposed Protected Forest Land to be diverted for Laying of Underground… — lapsed, 2.6 km away
- Proposed Protected Forest Land to be diverted for Lying 4" dia CS and 125mm… — more information requested, 3.3 km away
- Amended BharatNet Project (Kyara-Bareilly) — lapsed, 4.9 km away
- Improvement & Up-gradation of NH-530B section of Western Spur of Bareilly in… — in-principle approval, conditions pending, 5.2 km away
- Laying of Underground Electrical Cable at Bareilly - Rampur road (Old NH-24)… — lapsed, 5.7 km away
- Forest Land Proposed to be diverted for approach access to HPCL Retail Outlet… — forest land use approved, 5.9 km away
- Proposed Protected Forest Land To be diverted for Road Strengthening &… — more information requested, 6.1 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.