Environmental approval grantedIndustry · Gorakhpur, Uttar Pradesh

Expansion of Integrated Steel Plant - Pellet Plant (7,92,000 TPA to 9,90,000 TPA), Sponge iron plant (6,60,000 TPA to 7,26,000 TPA), MS Billets (6,53,400 TPA to 8,00,250 TPA), Rolling mill (6,53,400 TPA to 7,85,000 TPA) & Captive power plant (80.5 MW to 120 MW) At Plot No.AL5, Sector-23, GIDA Industrial Area, Tehsil Sahjanwa, District Gorakhpur, U.P. by M/s. Gallantt Ispat Limited

Expansion of Integrated Steel Plant - Pellet Plant (7,92,000 TPA to 9,90,000 TPA), Sponge iron plant (6,60,000 TPA to 7,26,000 TPA), MS Billets (6,53,400 TPA to 8,00,250 TPA), Rolling mill (6,53,400 TPA to 7,85,000 TPA) & Captive power plant (80.5 MW to 120 MW) At Plot No.AL5, Sector-23, GIDA Industrial Area, Tehsil Sahjanwa, District Gorakhpur, U.P. by M/s. Gallantt Ispat Limited is an approved industrial project in Rahimabad, Sahjanwa, Gorakhpur, Uttar Pradesh. The site covers 125.7 acres. Its stated project cost is ₹852.5 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 12 Nov 2026).

See it on the live map All projects in Gorakhpur

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

StatusEnvironmental approval granted
Status since12 Nov 2026
Application filed9 Sept 2026
Approval soughtEnvironmental approval
Application typeExpansion
SectorIndustry
ApplicantGallantt Ispat Limited
Land area125.7 acres (50.9 ha)
Project cost₹852.5 crore
Village / localityRahimabad
Taluk / tehsilSahjanwa
DistrictGorakhpur
StateUttar Pradesh
Location fromSite boundary on record
Our referenceWID-UP-04086

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Expansion filed 9 Sept 2026 (this page)Environmental approval granted125.7 acres₹852.5 crore
Early planning filed 29 Jul 2025Cleared for impact study125.7 acres₹852.5 crore

In context

14 applications in Gorakhpur since January 2022 are in the same category (Industry): 13 approved, 1 filed or under review, and 0 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 125.7 acres, this one is larger than 64% of them.

14 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Rahimabad, Sahjanwa, Gorakhpur, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Gallantt Ispat Limited in Gorakhpur

3 Gallantt Ispat projects in Gorakhpur
All 5 Gallantt Ispat projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.