What is Allabuxpur Soil Mining Project?
Allabuxpur Soil Mining Project is a proposed mining project in Bakhshpur, Garhmukteshwar, Hapur, Uttar Pradesh. The site covers 4.6 acres.
Who is building it?
The applicant is Amit.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Bakhshpur, Garhmukteshwar, Hapur, Uttar Pradesh.
How big is it?
It has a stated cost of ₹20 lakh and a site of 4.6 acres.
When was it filed?
The application was filed on 21 Oct 2026.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 24 Oct 2026 |
| Application filed | 21 Oct 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Amit |
| Land area | 4.6 acres (1.9 ha) |
| Project cost | ₹20 lakh |
| Village / locality | Bakhshpur |
| Taluk / tehsil | Garhmukteshwar |
| District | Hapur |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-04879 |
In context
17 applications in Hapur since January 2022 are in the same category (Mining): 9 approved, 7 filed or under review, and 1 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 4.6 acres, this one is larger than 59% of them.
No other mining lease on record is within 500 m of this site; 3 have applied within 5 km.
Where it is
Bakhshpur, Garhmukteshwar, Hapur, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Allabuxpur Soil Mining Project — under environmental review, 250 m away
- Allabuxpur Soil Mining Project — under environmental review, 250 m away
- "Ordinary Earth Mine" — lapsed, 600 m away
- "Ordinary Earth Mine", Village- Bagadpur, Gata No.- 695kh & 699, Lease Area-… — environmental approval granted, 650 m away
- "Ordinary Earth Mine", Village- Bagadpur, Gata No.- 692, 693 & 695कमि, Area-… — environmental approval granted, 650 m away
- Diversion of 0.150 Ha. of Protected Forest Land for proposed IGL Laying of 125… — in-principle approval, conditions pending, 1.3 km away
- Diversion of 0.099 ha of Protected Forest Land under approach road for… — forest land use approved, 1.3 km away
- Proposed Forest Land to be Diverted for Entry/Exit Approach to HPCL-Mittal… — lapsed, 1.8 km away