Forest land use approvedPower · Aligarh, Uttar Pradesh

Diversion of Protected Forest Land for Construction of underground 33 KV line from 132 KV substation, Khair to Gaumat Chauraha through underground cable and from Gaumat Chauraha to under construction 33/11 KV substation, Gaumat, Aligarh through overhead cable

Diversion of Protected Forest Land for Construction of underground 33 KV line from 132 KV substation, Khair to Gaumat Chauraha through underground cable and from Gaumat Chauraha to under construction 33/11 KV substation, Gaumat, Aligarh through overhead cable is an approved power project in Chamr Nagariya, Khair, Aligarh, Uttar Pradesh. The site covers 0.2 acres. Its stated project cost is ₹9 crore. As of 27 Nov 2026, its status is “Forest land use approved” (since 28 Oct 2026).

See it on the live map All projects in Aligarh

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Diversion of Protected Forest Land for Construction of underground 33 KV line from 132 KV substation, Khair to Gaumat Chauraha through underground cable and from Gaumat Chauraha to under construction 33/11 KV substation, Gaumat, Aligarh through overhead cable is an approved power project in Chamr Nagariya, Khair, Aligarh, Uttar Pradesh. The site covers 0.2 acres.

Who is building it?

The applicant is Dakshinanchal Vidyut Vitran Nigam Limited.

Has it been approved?

Yes. Its status is “Forest land use approved” (since 28 Oct 2026), as of 27 Nov 2026.

Where is it?

In Chamr Nagariya, Khair, Aligarh, Uttar Pradesh.

How big is it?

It has a stated cost of ₹9 crore; a site of 0.2 acres and 500 m² of forest land.

When was it filed?

The application was filed on 8 Jun 2026.

Project details

Official titleDiversion of Protected Forest Land for Construction of underground 33 KV line from 132 KV substation, Khair to Gaumat Chauraha through underground cable and from Gaumat Chauraha to under construction 33/11 KV substation, Gaumat, Aligarh through overhead cable in District- Aligarh by Electrical Secondary Works Division, Dakshinanchal Vidyut Vitran Nigam Limited, Aligarh.
StatusForest land use approved
Status since28 Oct 2026
Application filed8 Jun 2026
Approval soughtForest land use
Application typeNew project
SectorPower
ApplicantDakshinanchal Vidyut Vitran Nigam Limited
Land area900 m²
Forest land500 m²
Project cost₹9 crore
Village / localityChamr Nagariya
Taluk / tehsilKhair
DistrictAligarh
StateUttar Pradesh
Location fromSite boundary on record
Our referenceWID-UP-05607

In context

1 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Chamr Nagariya, Khair, Aligarh, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Dakshinanchal Vidyut Vitran Nigam Limited in Aligarh

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.