Quick answers
What is this project?
Project for Laying of Carbon Steel Gas Pipeline by Indian Oil-Adani Gas Private Limited is a proposed pipeline project in Kanhoi, Gabhana, Aligarh, Uttar Pradesh. The site covers 4.1 acres.
Who is building it?
The applicant is Indianoil Adani Gas PVT LTD.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Kanhoi, Gabhana, Aligarh, Uttar Pradesh.
How big is it?
It has a stated cost of ₹25 crore; a site of 4.1 acres and 2.2 acres (0.9 ha) of forest land.
When was it filed?
The application was filed on 12 Oct 2025.
Project details
| Official title | Project for Laying of Carbon Steel Gas Pipeline by Indian Oil-Adani Gas Private Limited along with road on Pahavati to Gabhana (NH-34 ) km Ch. 108 to 113.10, Gabhana to Bhukhrawali (NH-34) km Ch 113.10 to 129.1, Panethi to Jasrathpur (NH-34) km Ch. 156.0 to 158.0, Lahosara Bisawan to Nada Pul (NH-334D) km Ch. 73.00 to 75.80, Sasni Gate to Rishi Rawat HPCL Pump (SH-80) km Ch. 0.70 to 2.20 & Green View Resort to Shiva Filling CNG Station (NH-509) km Ch. 157.60 to 160.0 Total 29.80 km in Aligarh |
|---|---|
| Status | More information requested |
| Status since | 17 Jun 2026 |
| Application filed | 12 Oct 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Pipelines |
| Applicant | Indianoil Adani Gas PVT LTD |
| Land area | 4.1 acres (1.7 ha) |
| Forest land | 2.2 acres (0.9 ha) |
| Project cost | ₹25 crore |
| Village / locality | Kanhoi |
| Taluk / tehsil | Gabhana |
| District | Aligarh |
| State | Uttar Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-UP-05674 |
In context
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kanhoi, Gabhana, Aligarh, Uttar Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- DIVERSION OF 4.465 ha. PROTECTED FOREST LAND FOR STRENTHENING AND WIDENING OF… — forest land use approved, 1.1 km away
- Proposed Commercial Building & Bus Stand of Uttar Pradesh Parivahan Nigam at… — more information requested, 2.5 km away
- UP Defence Industrial Corridor – Aligarh Node (Phase- II) — cleared for impact study, 2.7 km away
- Diversion of protected forest land for construction of approach road to the… — in-principle approval, conditions pending, 5.1 km away
- Diversion of 0.0428 Hectare of protected Forest land under Social forestry… — forest land use approved, 6.2 km away
- Proposed forest land to be diverted for construction of Approach Road — in-principle approval, conditions pending, 6.5 km away
- Proposed Protected Forest Land to be diverted for Laying of Underground… — more information requested, 6.6 km away
- Proposed Protected Forest Land to Be Diverted by Hindustan Petroleum… — lapsed, 6.8 km away
More from Indianoil Adani Gas PVT LTD in Aligarh
- Diversion of protected forest land for Construction of approach road to the… — in-principle approval, conditions pending
- Laying of Carbon Steel Gas Pipeline — forest land use approved
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.