Iron Ore Beneficiation Plant (2x1.5 MTPA) - 3.0 MTPA, Pellet Plant (2 x 1.2 MTPA) – 2.4 MTPA, Producer Gas Plant (14 x 5000 NM3/Hr.)- 588 MNM3 per annum, DRI Kilns (8x600 TPD) – 1.68 MTPA, WHRB Power through DRI kilns – (8 x 15 MW)-120 MW ,Through BF - 18 MW , Through Coke Oven- 15 MW and CFBC based Power Plant of (2 x 15 MW)- 30 MW, SMS – IF (18 x 20 T) with LRF (6 X 20 T)- 1.26 MTPA, BOF (1 x 50 T) with LRF (1 x 50 T) and VD unit (1 x 50 T)- 0.525 MTPA and EAF (1 X 50 T)with LRF (1 x 50 T) - 0.175 MTPA, Rolling Mill through hot charging (3 x 1000 TPD) - 1.05 MTPA, Sinter Plant (1x 100 m2) – 1.092 MTPA ,Blast Furnace (1x750 m3) – 0.7875 MTPA, Coke Oven Plant (Non recovery) – 0.5 MTPA, Ferro Alloys (4 x 9 MVA)- 0.084 MTPA, Oxygen Plant (1x250 TPD) -0.087 MTPA, Lime & Dolomite Plant (1x 450 TPD) – 0.1575 MTPA, Brick Manufacturing Unit -350 Million Bricks/Year & Slag Recycling Plant (1 x 150 TPD) – 0.0525 MTPA is an approved industrial project in Lachhmanpur, Raghunathpur - I, Puruliya, West Bengal. The site covers 600 acres.
Who is building it?
The applicant is Shyam Steel Works (P) Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 29 Aug 2023), as of 27 Nov 2026.
Where is it?
In Lachhmanpur, Raghunathpur - I, Puruliya, West Bengal.
How big is it?
It has a stated cost of ₹4,591 crore and a site of 600 acres.
When was it filed?
The application was filed on 29 Aug 2023.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 29 Aug 2023 |
| Application filed | 29 Aug 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Shyam Steel Works (P) Limited |
| Land area | 600 acres (242.8 ha) |
| Project cost | ₹4,591 crore |
| Village / locality | Lachhmanpur |
| Taluk / tehsil | Raghunathpur - I |
| District | Puruliya |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-00054 |
In context
33 applications in Puruliya since January 2022 are in the same category (Industry): 22 approved, 5 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 600 acres, this one is larger than 76% of them.
9 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Lachhmanpur, Raghunathpur - I, Puruliya, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Shyam Steel Railway Siding — forest land use approved, 1.9 km away
- Greenfield Steel Plant for Production of 1.7 MTPA Pellets, 1.320 MTPA Sponge… — returned to applicant, 2.3 km away
- Integrated Steel Plant of 4.5 Million Tpa (Finished Steel) With 680 MW Captive… — withdrawn, 3.8 km away
- Integrated Steel Plant of 09 Million Ton Per Annum (finished steel) with 1260… — under environmental review, 3.9 km away
- Integrated Steel Plant of 09 Million Ton Per Annum (finished steel) with 1260… — withdrawn, 3.9 km away
- Upardanga Granite Stone Quarry — environmental approval granted, 4.2 km away
- Surface Based Water Supply Scheme Northern Zone Under Purulia Division, Phe Dte. — lapsed, 4.4 km away