What is this project?
Integrated Steel Plant of 09 Million Ton Per Annum (finished steel) with 1260 MW Captive Power Plant at Mouja- Durmut (J.L. No. 155), Layekdi (J.L. No. 153) & Nutandih (J.L. No. 157), P.S. – Raghunathpur, Dist. – Purulia, West Bengal is a proposed industrial project in Goaladi, Raghunathpur - I, Puruliya, West Bengal. The site covers 850 acres.
Who is building it?
The applicant is Orissa Alloy Steel PVT. LTD..
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Goaladi, Raghunathpur - I, Puruliya, West Bengal.
How big is it?
It has a stated cost of ₹12,000 crore and a site of 850 acres.
When was it filed?
The application was filed on 27 Jul 2026.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 8 Aug 2026 |
| Application filed | 27 Jul 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Orissa Alloy Steel PVT. LTD. |
| Land area | 850 acres (344 ha) |
| Project cost | ₹12,000 crore |
| Village / locality | Goaladi |
| Taluk / tehsil | Raghunathpur - I |
| District | Puruliya |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-01654 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Early planning filed 27 Jul 2026 (this page) | Under environmental review | 850 acres | ₹12,000 crore |
| Early planning filed 16 Jul 2026 | Withdrawn | 850 acres | ₹12,000 crore |
In context
33 applications in Puruliya since January 2022 are in the same category (Industry): 22 approved, 5 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 850 acres, this one is larger than 88% of them.
6 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Goaladi, Raghunathpur - I, Puruliya, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Integrated Steel Plant of 09 Million Ton Per Annum (finished steel) with 1260… — withdrawn, 0 m away
- Integrated Steel Plant of 4.5 Million Tpa (Finished Steel) With 680 MW Captive… — withdrawn, 50 m away
- Iron Ore Beneficiation Plant (2x1.5 MTPA) - 3.0 MTPA, Pellet Plant (2 x 1.2… — environmental approval granted, 3.9 km away
- Proposed DVC, Raghunathpur Thermal Power Project-PH-II (2x660 MW) — environmental approval granted, 4.3 km away
- Proposed DVC, Raghunathpur Thermal Power Project-PH-II (2x660 MW) — cleared for impact study, 4.3 km away
- Upardanga Granite Stone Quarry — environmental approval granted, 4.4 km away
- Shyam Steel Railway Siding — forest land use approved, 4.9 km away
- Greenfield Steel Plant for production of 51500TPA(Max) Ferro Alloys by 2x9MVA… — environmental approval granted, 6.1 km away
More from Orissa Alloy Steel PVT. LTD. in Puruliya
3 Orissa Alloy Steel projects in Puruliya
All 12 Orissa Alloy Steel projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.