| Official title | Expansion of Integrated Steel Plant from 2.0 million TPA with 385 MW CPP to Integrated Steel Plant of capacity 4.2 million TPA (Finished Steel) along with 536 MW Captive Power Plant |
|---|---|
| Status | Cleared for impact study |
| Status since | 1 May 2023 |
| Application filed | 25 Apr 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Orissa Metallurgical Industry Private Limited |
| Land area | 421.8 acres (170.7 ha) |
| Project cost | ₹3,500 crore |
| Village / locality | Amba |
| Taluk / tehsil | Kharagpur - I |
| District | Medinipur West |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-00135 |
In context
43 applications in Medinipur West since January 2022 are in the same category (Industry): 27 approved, 10 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 421.8 acres, this one is larger than 77% of them.
27 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Amba, Kharagpur - I, Medinipur West, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Integrated Steel Plant from 2.0 million TPA with 385 MW CPP to… — environmental approval granted, 50 m away
- Expansion of Integrated Steel Plant from 2.0 million TPA with 385 MW CPP to… — environmental approval granted, 50 m away
- Expansion of Integrated Steel Plant from 2.0 million TPA with 385 MW CPP to… — environmental approval granted, 50 m away
- Proposed expansion of Integrated Steel Plant 4.2 million TPA (Finished Steel) — returned to applicant, 300 m away
- 'Splitting of Environment Clearance' - 10 x 20 T (0.6 MTPA) Induction Furnace… — environmental approval granted, 650 m away
- Assessment of No Increase in Pollution Load for expansion of DRI plant… — initial checks, 650 m away
- 'Change of name of the company in Environment Clearance accorded units'-… — environmental approval granted, 700 m away
- Proposed Expansion by Installation of Induction Furnace (5 X 25 T) With… — environmental approval granted, 1 km away
More from Orissa Metallurgical Industry Private Limited in Medinipur West
- Expansion of Integrated Steel Plant from 2.0 million TPA with 385 MW CPP to… — initial checks
- Expansion of Integrated Steel Plant from 2.0 million TPA with 385 MW CPP to… — environmental approval granted
- 'change of Name of the Company in Environment Clearance Accorded Units'-… — environmental approval granted
- Expansion of Integrated Steel Plant from 2.0 million TPA with 385 MW CPP to… — environmental approval granted
- 'Change of name of the company in Environment Clearance accorded units'-… — environmental approval granted
- 'change of Name of Environment Clearance Accorded Units'- Proposed Expansion… — environmental approval granted
All 8 Orissa Metallurgical Industry projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.