Quick answers
What is this project?
Expansion of Existing Secondary Metallurgical Unit (For Production of MS Ingot / Billet and Rolling Mill Products) by replacement of Existing 2 x 8T Induction Furnace by 2 x 20T Induction Furnace and Installation of Additional 4 x 20T Induction Furnaces, Additional Rolling Mill, and Wire Rod Mill is a proposed industrial project in Nidhirampur, Gangajalghati, Bankura, West Bengal. The site covers 22.3 acres.
Who is building it?
The applicant is Shree Ramdoot Rollers PVT LTD.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 18 Nov 2024), as of 27 Nov 2026.
Where is it?
In Nidhirampur, Gangajalghati, Bankura, West Bengal.
How big is it?
It has a stated cost of ₹135.9 crore and a site of 22.3 acres.
When was it filed?
The application was filed on 13 Sept 2024.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 18 Nov 2024 |
| Application filed | 13 Sept 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Shree Ramdoot Rollers PVT LTD |
| Land area | 22.3 acres (9 ha) |
| Project cost | ₹135.9 crore |
| Village / locality | Nidhirampur |
| Taluk / tehsil | Gangajalghati |
| District | Bankura |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-00844 |
In context
69 applications in Bankura since January 2022 are in the same category (Industry): 29 approved, 23 filed or under review, and 17 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 22.3 acres, this one is larger than 54% of them.
13 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Nidhirampur, Gangajalghati, Bankura, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Environmental Clearance for the expansion of existing secondary metallurgical… — initial checks, 0 m away
- Environmental Clearance for the expansion of existing secondary metallurgical… — under environmental review, 0 m away
- The proposed expansion proposal containing additional installing of 2 X20 MT… — environmental approval granted, 0 m away
- Environmental Clearance for the expansion of existing secondary metallurgical… — not approved, 0 m away
- Expansion in Steel Plant for Increasing Capacity of Sms Unit From 180805 Tpa… — cleared for impact study, 200 m away
- Application for extension of the validity of Environmental Clearance Vide no.… — environmental approval granted, 1.8 km away
- Industrial project by Jk Lakshmi Cement Limited — environmental approval granted, 2 km away
- Extension of validity of Environmental clearance of Propose 1.5 MTPA Cement… — environmental approval granted, 2 km away
More from Shree Ramdoot Rollers PVT LTD in Bankura
- Environmental Clearance for the expansion of existing secondary metallurgical… — initial checks
- Environmental Clearance for the expansion of existing secondary metallurgical… — under environmental review
- Environmental Clearance for the expansion of existing secondary metallurgical… — not approved
- Expansion in Steel Plant for Increasing Capacity of Sms Unit From 180805 Tpa… — cleared for impact study
- The proposed expansion proposal containing additional installing of 2 X20 MT… — environmental approval granted
All 6 Shree Ramdoot Rollers projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.