Quick answers
What is this project?
Proposed Expansion of Existing Grain Based Distillery Plant Capacity From 100 Klpd to 150 Klpd Ethanol With No Increase of Pollution Load Within the Existing Plant is a proposed industrial project in Golgram, Galsi - I, Purba Bardhaman, West Bengal. The site covers 20.2 acres.
Who is building it?
The applicant is Greenosphere Renewable Energy Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Golgram, Galsi - I, Purba Bardhaman, West Bengal.
How big is it?
It has a stated cost of ₹113.7 crore and a site of 20.2 acres.
When was it filed?
The application was filed on 21 Mar 2026.
Project details
| Status | Initial checks |
|---|---|
| Status since | 21 Mar 2026 |
| Application filed | 21 Mar 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Greenosphere Renewable Energy Private Limited |
| Land area | 20.2 acres (8.2 ha) |
| Project cost | ₹113.7 crore |
| Village / locality | Golgram |
| Taluk / tehsil | Galsi - I |
| District | Purba Bardhaman |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-01756 |
In context
21 applications in Purba Bardhaman since January 2022 are in the same category (Industry): 9 approved, 8 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 20.2 acres, this one is smaller than 76% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Golgram, Galsi - I, Purba Bardhaman, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environmental Clearance for Proposed 100 KLPD Grain based… — environmental approval granted, 0 m away
- Proposed Steel Plant (Green-field Project) for installation of 2x500 TPD DRI… — returned to applicant, 7.6 km away
- Taherpur Sand Mine — environmental approval granted, 11.3 km away
- Taherpur Sand Mine — environmental approval granted, 11.3 km away
- Taherpur Sand Mine — cleared for impact study, 11.3 km away
- Dumur Sand Mine — environmental approval granted, 11.4 km away
- Dumur Sand Mine — cleared for impact study, 11.4 km away
- Shikarpur Sand Mine (MIN_EBUR_28) — environmental approval granted, 11.4 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.