Quick answers
What is this project?
Proposed Steel Plant (Green-field Project) for installation of 2x500 TPD DRI Kilns, 8x20 T Induction Furnaces is a proposed industrial project in Palitpur, Burdwan - I, Purba Bardhaman, West Bengal. The site covers 161.7 acres.
Who is building it?
The applicant is HMB Steel private limited.
Has it been approved?
Not yet. The application is still under review: its status is “Returned to applicant”, as of 27 Nov 2026.
Where is it?
In Palitpur, Burdwan - I, Purba Bardhaman, West Bengal.
How big is it?
It has a stated cost of ₹810 crore and a site of 161.7 acres.
When was it filed?
The application was filed on 18 Nov 2025.
One of 3 filings for this project. The project's main page, with every filing and where each stands: Proposed Steel Plant (Green-field Project) for installation of 2x500 TPD DRI Kilns, 8x20…
Project details
| Official title | Proposed Steel Plant (Green-field Project) for installation of 2x500 TPD DRI Kilns, 8x20 T Induction Furnaces along with matching LRF & CCM, 1x10 T AOD & 1x10 T VOD & 1X20 TPH capacity Slag Crusher Unit, 5x9 MVA capacity Submerged Arc Furnaces, 0.55 MTPA capacity Rolling Mill along with 1x30 TPH Re-heating Furnace (stand by) & 2x4000 Nm3/Hr capacity Producer Gas Plant (stand by), 60,000 TPA capacity Galvanising Unit and 30 MW capacity Captive Power Plant (24 MW WHRB + 6 MW AFBC). |
|---|---|
| Status | Returned to applicant |
| Status since | 5 Dec 2025 |
| Application filed | 18 Nov 2025 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | HMB Steel private limited |
| Land area | 161.7 acres (65.4 ha) |
| Project cost | ₹810 crore |
| Village / locality | Palitpur |
| Taluk / tehsil | Burdwan - I |
| District | Purba Bardhaman |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-00990 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 10 Feb 2026 | Environmental approval granted | 197.9 acres | ₹810 crore |
| New project filed 18 Nov 2025 (this page) | Returned to applicant | 161.7 acres | ₹810 crore |
| Early planning filed 9 Apr 2025 | Cleared for impact study | 197.9 acres | ₹810 crore |
In context
21 applications in Purba Bardhaman since January 2022 are in the same category (Industry): 9 approved, 8 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 161.7 acres, this one is larger than 86% of them.
Where it is
Palitpur, Burdwan - I, Purba Bardhaman, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environmental Clearance for Proposed 100 KLPD Grain based… — environmental approval granted, 7.6 km away
- Proposed Expansion of Existing Grain Based Distillery Plant Capacity From 100… — initial checks, 7.6 km away
- Proposed Steel Plant (Green-field Project) for installation of 2x500 TPD DRI… — environmental approval granted, 10.5 km away
- Proposed Steel Plant (Green-field Project) for installation of 2x500 TPD DRI… — cleared for impact study, 10.5 km away
- Durgapur Haldia Section of Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL)… — forest land use approved, 10.7 km away
- Gohogram sand Mine — environmental approval granted, 14.8 km away
- Gohogram Sand Mine — environmental approval granted, 14.8 km away
- Gohogram Sand Mine on Damodar River — environmental approval granted, 14.9 km away
All 3 HMB Steel projects across India