One of 2 filings for this project. The project's main page, with every filing and where each stands: Hot & Cold Rolling Mill Plant at Plot No.220 (Full), 221 (P) & 222 (P), Nachan Road,…
Project details
| Official title | Proposed Installation of Hot & Cold Rolling Mill Plant at Plot No.220 (Full), 221 (P) & 222 (P), Nachan Road, Mouza-Kamalpur, J.L No. 47, P.S & P.O.-Durgapur, District-Paschim Bardhaman, State-West Bengal by M/s Sharp Ferro Alloys Ltd. |
|---|---|
| Status | Lapsed |
| Status since | 21 Nov 2026 |
| Application filed | 27 Feb 2026 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Sharp Ferro Alloys Limited |
| Land area | 12.4 acres (5 ha) |
| Project cost | ₹30 crore |
| Village / locality | Kamalpur |
| Taluk / tehsil | Faridpur Durgapur |
| District | Paschim Bardhaman |
| State | West Bengal |
| Location from | Site boundary on record |
| Our reference | WID-WB-01826 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 27 Feb 2026 (this page) | Lapsed | 12.4 acres | ₹30 crore |
| Early planning filed 6 Sept 2023 | Cleared for impact study | 12.4 acres | ₹30 crore |
In context
169 applications in Paschim Bardhaman since January 2022 are in the same category (Industry): 81 approved, 49 filed or under review, and 39 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 12.4 acres, this one is smaller than 77% of them.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kamalpur, Faridpur Durgapur, Paschim Bardhaman, West Bengal. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Hot & Cold Rolling Mill Plant at Plot No.220 (Full), 221 (P) & 222 (P), Nachan… — cleared for impact study, 0 m away
- Enhancement of MS Ingots/ Billets production from 61,800 TPA to 157,620 TPA — cleared for impact study, 1.6 km away
- Proposed expansion of existing steel plant consisting of 2x12T Induction… — lapsed, 3.2 km away
- Proposal for Installation of Petrol Pump at Tagore Avenue Durgapur, WB — lapsed, 3.3 km away
- Proposed Expansion of Ferro Alloy Plant by Installing 1 X 6.5 MVA Submerged… — under environmental review, 4.3 km away
- Proposed Expansion of Ferro Alloy Plant by Installing 1 X 6.5 MVA Submerged… — cleared for impact study, 4.3 km away
- Proposed Expansion of Ferro Alloy Plant By Installing 1 X 6.5 MVA Submerged… — returned to applicant, 4.3 km away
- 4x6 Tonnes Induction Furnaces — cleared for impact study, 4.5 km away
All 3 Sharp Ferro Alloys projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.