Jayaswal Neco Industries upcoming projects

Jayaswal Neco Industries Limited has filed 12 projects for environmental, forest, wildlife or coastal approval since January 2022: 5 approved and 4 awaiting a decision. They are in Narayanpur, Bilaspur and Raipur (2 states), covering 4,229.1 acres with a stated cost of ₹35,932.4 crore. The latest was filed on 6 Aug 2026.

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

12projects filed
4awaiting approval
5districts

All 12 projects, newest first

ProjectTypeSizeStatusFiled
Integrated Steel Plant Comprising of DRI Plant - 0.6 MTPA, SMS - 0.55 MTPA, Rolling Mill…
Utgan, Bilaspur, Chhattisgarh
Industry224.9 acresUnder environmental review6 Aug 2026
Expansion cum modification of Integrated Steel plant comprising Sponge Iron Plant of…
Utgan, Bilaspur, Chhattisgarh
Industry224.9 acresReturned to applicant9 Jun 2026
0.50 MTPA Integrated Steel Plant of M/s Jayaswal Neco Industries Limited
Ameri Akbari, Bilaspur, Chhattisgarh
Industry224.9 acresWithdrawn12 May 2026
Enhancement of Iron Ore Mining Capacity from the present 2.95 MTPA to 6.00 MTPA…
Chhota Dongar R F, Narayanpur, Chhattisgarh
Mining475.1 acresEnvironmental approval granted29 Aug 2025
Laying of Pipe Line for Chhotedongar Iron Ore Mine Over an Area of 0.406 Ha of Forest Land
Chhota Dongar R F, Narayanpur, Chhattisgarh
Pipelines4 acresForest land use approved5 Apr 2025
Amendment in Environment Clearance granted for lron Ore mining of 1.0 MTPA in lease area…
Metabodeli, Uttar Bastar Kanker, Chhattisgarh
Mining61.8 acresEnvironmental approval granted26 Feb 2025
Laying of Pipe Line for Chhotedongar Iron Ore Mine area 0.41 hectare Detail
Chhota Dongar R F, Narayanpur, Chhattisgarh
Pipelines4.1 acresLapsed19 Nov 2024
Laying of Pipe Line for Chhotedongar Iron Ore Mine area 0.41 hectare Detail
Chhota Dongar R F, Narayanpur, Chhattisgarh
Pipelines4.1 acresLapsed30 May 2024
Enhancement of Iron Ore Mining Capacity from the present 2.95 MTPA to 6.00 MTPA…
Chhota Dongar R F, Narayanpur, Chhattisgarh
Mining475.1 acresCleared for impact study2 Mar 2024
Diversion of 61.45 Ha Forest Land for Ramdongri Manganese Ore Minge
Ramdongari, Nagpur, Maharashtra
Mining151.8 acresMore information requested18 Apr 2023
Expansion & Modernization of Integrated Steel Plant-BF–0.75 to 2.0 MTPA (0.75 to 1 MTPA…
Dhaneli, Raipur, Chhattisgarh
Industry1,189.3 acresEnvironmental approval granted2 Mar 2023
Expansion & Modernization of Integrated Steel Plant-BF–0.75 to 2.0 MTPA (0.75 to 1 MTPA…
Giraud, Raipur, Chhattisgarh
Industry1,189.3 acresMore information requested24 Feb 2023

Jayaswal Neco Industries projects by city

Where Jayaswal Neco Industries is building

Questions people ask

How many projects has Jayaswal Neco Industries filed?

12 since January 2022, of which 5 are approved and 4 are awaiting a decision.

Where are Jayaswal Neco Industries's projects?

Mostly in Narayanpur, Chhattisgarh (5), Bilaspur, Chhattisgarh (3), Raipur, Chhattisgarh (2), Uttar Bastar Kanker, Chhattisgarh (1) and Nagpur, Maharashtra (1).

What did Jayaswal Neco Industries file most recently?

Integrated Steel Plant Comprising of DRI Plant - 0.6 MTPA, SMS - 0.55 MTPA, Rolling Mill - 0.50 MTPA, Captive Power Plant - 140MW, Oxygen Plant - 50 TPD, Coke Oven - 1.0 MTPA, Slag Crushing Unit - 0.1 MTPA & Fly Ash Bricks Making Plant – 0.1 MTPA (25000-27000 Nos.) by M/s Jayaswal Neco Industries Limited in Utgan, Bilaspur, filed on 6 Aug 2026. Status: Under environmental review.

About this information

Compiled from publicly available approval records, grouped by the applicant's registered name. What is Developing? is not affiliated with Jayaswal Neco Industries; the badge is generated from its name. Group companies that file under different names may appear on separate pages. Statuses can change between our updates; check with the authority before making decisions. Spotted a mistake? Tell us.