Projects by type
| Type | Projects |
|---|---|
| Mining | 50 |
| Roads & highways | 10 |
| Buildings & townships | 5 |
| Water & irrigation | 4 |
| Industry | 3 |
| Pipelines | 2 |
| Survey & exploration | 2 |
| Telecom | 2 |
| Other | 1 |
Where they are in the approval process
| Status | Projects |
|---|---|
| Filed or under review | 25 |
| In-principle approval | 1 |
| Approved | 32 |
| Not approved | 1 |
| Withdrawn or lapsed | 20 |
Recently approved
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| Aayush Agrawal Sonpur, Ramanujnagar | Mining | 3.5 acres | Environmental approval granted | 17 Jul 2026 |
| Devri-Dumhat Block Chandaura, Pratappur | Other | 2,471.1 acres | Forest land use approved | 12 Jan 2025 |
| Harratikra-1 Sand Mine Harratikura, Surajpur | Mining | 9.9 acres | Environmental approval granted | 27 Apr 2026 |
| Exploration (Core Hole Drilling) of Coal Bed Methane (CBM) in block SR-ONHP(CBM)-2021/6… Pal Danauli, Oudgi | Mining | 1,44,484.8 acres | Environmental approval granted | 3 Feb 2026 |
| Abhishek Kumar Goyal Harratikra, Surajpur | Mining | 7.4 acres | Environmental approval granted | 18 Apr 2026 |
| Bhaskarpara open cast cum underground coal mine with production capacity of 1.0 MTPA to… Kurridih, Bhaiyathan | Mining | 2,303 acres | Environmental approval granted | 24 Mar 2026 |
| Sandeep Kumar Agrawal Pawanpur, Ramanujnagar | Mining | 4.9 acres | Environmental approval granted | 10 Feb 2026 |
| Proposed Forest Diversion for of Proposed Approach Road From National Highway to Parsa… Pidiya R F, Premnagar | Roads & highways | 5.1 acres | Forest land use approved | 3 Sept 2025 |
| Shiwani Ug Mine Banshipur, Pratappur | Mining | 2,148.9 acres | Forest land use approved | 3 Jan 2024 |
| Shiwani UG Mine Banshipur, Pratappur | Mining | 2,370.5 acres | Forest land use approved | 20 Dec 2023 |
Recently filed
| Project | Type | Size | Status | Filed |
|---|---|---|---|---|
| PMGSY Road L311-Odgi Nawatola Road Km. 8.20 To Ghuidih Pandopara Belmi, Oudgi | Roads & highways | 20.7 acres | Under wildlife review | 19 Nov 2026 |
| Proposed amendment in process with expansion of rolling mill capacity from 59400 TPA to… Girvarganj, Surajpur | Industry | 7.8 acres | Initial checks | 15 Nov 2026 |
| PMGSY Road L311-Odgi Nawatola Road Km. 8.20 To Ghuidih Pandopara Belmi, Oudgi | Roads & highways | 20.7 acres | Not approved | 10 Nov 2026 |
| Proposed 2nd Phase Capacity Optimization and Expansion from 1.20 MTPA to 1.40 MTPA… Barsara, Bhaiyathan | Mining | 2,303 acres | Under environmental review | 3 Nov 2026 |
| City Gas Distribution Network by BPCL Ganeshpur, Surajpur | Pipelines | 0.5 acres | Initial checks | 19 Oct 2026 |
| Rolling Mill having a total project area of 7.787 Acres, located at Plot Nos. 94–115,… Girvarganj, Surajpur | Buildings & townships | 104.8 acres | Initial checks | 9 Oct 2026 |
| Ketki Expansion Underground Mine (Mdo Mode) Ketka, Surajpur | Mining | 1,355.7 acres | Under environmental review | 22 Sept 2026 |
| Sohagpur-1 Ordinary Sand Quarry, Area 2.500 Ha. Village Sohagpur, Project Proponent… Sohagpur, Surajpur | Mining | 6.2 acres | More information requested | 10 Sept 2026 |
| Umeshpur-1 Ordinary Sand Quarry, Area - 0.800 Ha, Village - Umeshpur, Project Prop. -… Umeshpur Alias Urchuma, Ramanujnagar | Mining | 2 acres | Under environmental review | 29 Aug 2026 |
| Shiwani Ug Mine Banshipur, Pratappur | Mining | 1,385 acres | Lapsed | 19 Aug 2026 |
| Bhaskarpara open cast cum underground coal mine with production capacity of 1.0 MTPA to… Kurridih, Bhaiyathan | Mining | 2,303 acres | Withdrawn | 28 Jul 2026 |
| Namadgiri 2 Sand Mine Surajpur, Surajpur | Mining | 8.6 acres | More information requested | 27 Jul 2026 |
| Aayush Agrawal Sonpur, Ramanujnagar | Mining | 3.5 acres | Environmental approval granted | 17 Jul 2026 |
| Tulesh Koshle Karkoti, Bhaiyathan | Mining | 7.4 acres | More information requested | 23 Jun 2026 |
| Namadgiri-1 Sand Mine Surajpur, Surajpur | Mining | 8.6 acres | More information requested | 15 Jun 2026 |
| Industrial project by UB Ventures Private Limited Girvarganj, Surajpur | Industry | 104.8 acres | Under environmental review | 31 May 2026 |
| Construction of L313 Moharshop Khas To KachhwariPMGSY Road Jurwanlan, Oudgi | Roads & highways | 6 acres | Decision issued | 27 May 2026 |
| Construction of L313 Moharshop Khas To KachhwariPMGSY Road Jurwanlan, Oudgi | Roads & highways | ₹6.3 crore | More information requested | 22 May 2026 |
| Sand Quarry Rajapur-2 Rajapur, Surajpur | Mining | 7.4 acres | Under environmental review | 22 May 2026 |
| Construction of PMGSY Road Khod Bajar To Chhatolibijo Chhatauli, Oudgi | Roads & highways | ₹6.2 crore | More information requested | 20 May 2026 |
| Construction of PMGSY Road L317-Khod Nawapra To Kesar Kesar, Oudgi | Roads & highways | 9.6 acres | More information requested | 20 May 2026 |
| Nareshpur Ordinary Sand Quaary, Area- 5.00 Ha, Village- Nareshpur, Project Proponent… Nareshpur, Surajpur | Mining | 12.4 acres | Lapsed | 20 May 2026 |
| Construction of PMGSY Road Khod Bajar To Chhatolibijo Chhatauli, Oudgi | Roads & highways | 6.9 acres | More information requested | 19 May 2026 |
| Construction of PMGSY Road L317-Khod Nawapra To Kesar Kesar, Oudgi | Roads & highways | 9.6 acres | More information requested | 19 May 2026 |
| 24.90 MW Jelha Small Hydro Electric Project Reserved Forest, Oudgi | Buildings & townships | 235.5 acres | Decision issued | 16 May 2026 |
| "Proposed Integrated Coal to Chemicals & Petrochemical based Products" by CG Syn-Gas &… Salka, Premnagar | Industry | 2,526.5 acres | Returned to applicant | 9 May 2026 |
| Harratikra-1 Sand Mine Harratikura, Surajpur | Mining | 9.9 acres | Environmental approval granted | 27 Apr 2026 |
| Abhishek Kumar Goyal Harratikra, Surajpur | Mining | 7.4 acres | Environmental approval granted | 18 Apr 2026 |
| Bhaskarpara open cast cum underground coal mine with production capacity of 1.0 MTPA to… Kurridih, Bhaiyathan | Mining | 2,303 acres | Environmental approval granted | 24 Mar 2026 |
| Sandeep Kumar Agrawal Pawanpur, Ramanujnagar | Mining | 4.9 acres | Environmental approval granted | 10 Feb 2026 |
| Exploration (Core Hole Drilling) of Coal Bed Methane (CBM) in block SR-ONHP(CBM)-2021/6… Pal Danauli, Oudgi | Mining | 1,44,484.8 acres | Environmental approval granted | 3 Feb 2026 |
| Detailed Exploration in Kotiya Coal Block Bagra, Pratappur | Survey & exploration | 6,084.5 acres | Lapsed | 3 Jan 2026 |
| Detailed Exploration in Bagra Coal Block Bagra, Pratappur | Survey & exploration | 6,011.2 acres | Lapsed | 6 Dec 2025 |
| Proposed Underground Datima Coal Mine (Targeted Capacity: 0.360 MTPA, Peak Capacity:… Kharsura, Surajpur | Mining | 1,996.4 acres | Environmental approval granted | 16 Oct 2025 |
| Ketki Expansion Underground Mine (Mdo Mode) Rf, Surajpur | Mining | 1,355.7 acres | Returned to applicant | 6 Oct 2025 |
| 6 MW Gej Hydro Power Project of Saffire Bio Energy LLP Sarastal, Premnagar | Water & irrigation | 10 acres | Lapsed | 3 Oct 2025 |
| Proposed Forest Diversion for of Proposed Approach Road From National Highway to Parsa… Pidiya R F, Premnagar | Roads & highways | 5.1 acres | Forest land use approved | 3 Sept 2025 |
| Devlopment of City Gas Distribution Network in Surajpur District Girvarganj, Surajpur | Pipelines | 7.3 acres | Lapsed | 25 Aug 2025 |
| Exploration (Core Hole Drilling) of Coal Bed Methane (CBM) in block SR-ONHP(CBM)-2021/6… Kharra, Oudgi | Mining | 1,44,484.8 acres | Environmental approval granted | 3 Jun 2025 |
| Ketki Expansion Underground Mine (Mdo Mode) Ketka, Surajpur | Mining | 1,355.7 acres | Cleared for impact study | 16 May 2025 |
| Amgaon Opencast Coal Mining Project Kot, Ramanujnagar | Mining | 1,979.9 acres | More information requested | 19 Apr 2025 |
| Khargaon coal Mine (the block) Kalyanpur (Koilari), Surajpur | Mining | 21,757 acres | Forest land use approved | 24 Mar 2025 |
| Jhigador Coal Mine Songara Protected Forest, Pratappur | Mining | 9,812.5 acres | Forest land use approved | 23 Mar 2025 |
| New Kumda Underground Coal Mine Balrampur, Surajpur | Mining | 1,233.1 acres | Lapsed | 11 Mar 2025 |
| Devri-Dumhat Block Chandaura, Pratappur | Other | 2,471.1 acres | Forest land use approved | 12 Jan 2025 |
| Proposed Underground Datima Coal Mine (Targeted Capacity: 0.360 MTPA, Peak Capacity:… Kumda, Surajpur | Mining | 1,996.4 acres | In-principle approval, conditions pending | 31 Dec 2024 |
| Rajapur Sand Quarry Rajapur, Surajpur | Mining | 7.4 acres | Environmental approval granted | 23 Dec 2024 |
| Kandrai Sand Quarry Kandrai, Surajpur | Mining | 7.4 acres | Environmental approval granted | 23 Dec 2024 |
| Jainagar Sand Quarry Jayanagar, Surajpur | Mining | 11.1 acres | Environmental approval granted | 23 Dec 2024 |
| Katkona Underground Coal Mine Forest, Oudgi | Mining | 494.7 acres | More information requested | 22 Dec 2024 |
Questions people ask
How many projects are planned in Surajpur?
79 projects in Surajpur have applied for approval since January 2022. 58 of them are active (not withdrawn, lapsed or rejected) and 26 are still awaiting a decision.
What was approved most recently in Surajpur?
Aayush Agrawal in Sonpur — “Environmental approval granted” on 16 Oct 2026.
How often is this list updated?
Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.
Most active developers in Surajpur
South Eastern Coalfields in Surajpur9
Shree Cement in Surajpur5- PIPrakash Industries in Surajpur4
Vedanta Limited(Division Cairn2- CMCentral Mine Planning2
- CNCg Natural Resources2
- CSChhattisgarh State Power2
Bharat Sanchar Nigam (BSNL)2