Project details
| Official title | Expansion of Steel Plant – DRI Kilns (Sponge Iron from 57,750 TPA to 2,88,750 TPA), Induction Furnaces along with CCM&LRF (Hot Billets / Billets / Ingots from 26,400 TPA to 2,97,000 TPA), WHRB based Power Plant from 4 MW to 22 MW, AFBC based Power Plant from 4 MW to 16 MW, Establishment of New Pellet Plant (0.6 MTPA), Gasifier for Pellet Plant (21,000 Nm3/hr),Rolling Mills (TMT bars / Structural Steel) - 3,30,000TPA), New Brick Manufacturing unit 33,000 Bricks/ day) |
|---|---|
| Status | Environmental approval granted |
| Status since | 17 Apr 2026 |
| Application filed | 13 Dec 2023 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Sugna Sponge & Power Private Limited |
| Land area | 75.1 acres (30.4 ha) |
| Project cost | ₹650.4 crore |
| Village / locality | Bhogasamudram |
| Taluk / tehsil | Tadpatri |
| District | Anantpur |
| State | Andhra Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AP-00324 |
In context
18 applications in Anantpur since January 2022 are in the same category (Industry): 11 approved, 3 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 75.1 acres, this one is smaller than 89% of them.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bhogasamudram, Tadpatri, Anantpur, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- As Per Requirement of Eia Notification, 2006 [as Amended to the Date] This Is… — initial checks, 0 m away
- Expansion of Steel Plant–Expansion Sponge Iron from 2,88,750 TPA to 18,72,750… — withdrawn, 550 m away
- Expansion–Sponge Iron-288750 TPA to1625250 TPA, IF with CCM-Hot Billets/MS… — cleared for impact study, 700 m away
- M/s. Megha Engineering Infrastructure Limited - Road Metal — environmental approval granted, 3.2 km away
- M/s. Megha Engineering Infrastructure Limited -Gravel Mine — environmental approval granted, 8.7 km away
- Amendment in Environmental Clearance for Extension of the time period for… — environmental approval granted, 10.2 km away
- Amendment in Environmental Clearance for Extension of the Time Period for… — returned to applicant, 10.2 km away
- Gudipadu Limestone Mine (Limestone Production: 4.70 MTPA with Total Excavation… — environmental approval granted, 10.2 km away
All 4 Sugna Sponge and Power projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.