What is Developing? Open the mapMap

Environmental approval grantedIndustry · Vizianagaram, Andhra Pradesh

Transfer of Environment clearance of M/s Hira Electro Smelters Private Limited to M/s Hira Electro Smelters Limited for submerged Arc Furnace (1x6 MVA), (2x 9 MVA) and (2 x 16.5 MVA) at Growth Centre, Bobbilli, Vizianagaram, District Andhra Pradesh 535 558.

Transfer of Environment clearance of M/s Hira Electro Smelters Private Limited to M/s Hira Electro Smelters Limited for submerged Arc Furnace (1x6 MVA), (2x 9 MVA) and (2 x 16.5 MVA) at Growth Centre, Bobbilli, Vizianagaram, District Andhra Pradesh 535 558 is an approved industrial project in Bobbili, Vizianagaram, Andhra Pradesh. The site covers 24 acres. Its stated project cost is ₹41 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 18 Jul 2023).

See it on the live map All projects in Vizianagaram

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Transfer of Environment clearance of M/s Hira Electro Smelters Private Limited to M/s Hira Electro Smelters Limited for submerged Arc Furnace (1x6 MVA), (2x 9 MVA) and (2 x 16.5 MVA) at Growth Centre, Bobbilli, Vizianagaram, District Andhra Pradesh 535 558 is an approved industrial project in Bobbili, Vizianagaram, Andhra Pradesh. The site covers 24 acres.

Who is building it?

The applicant is Hira Electro Smelters Limited.

Has it been approved?

Yes. Its status is “Environmental approval granted” (since 18 Jul 2023), as of 27 Nov 2026.

Where is it?

In Bobbili, Vizianagaram, Andhra Pradesh.

How big is it?

It has a stated cost of ₹41 crore and a site of 24 acres.

When was it filed?

The application was filed on 11 May 2023.

Project details

StatusEnvironmental approval granted
Status since18 Jul 2023
Application filed11 May 2023
Approval soughtEnvironmental approval
Application typeOwnership transfer
SectorIndustry
ApplicantHira Electro Smelters Limited
Land area24 acres (9.7 ha)
Project cost₹41 crore
Village / localityBobbili
Taluk / tehsilBobbili
DistrictVizianagaram
StateAndhra Pradesh
Location fromSite boundary on record
Our referenceWID-AP-00841

In context

40 applications in Vizianagaram since January 2022 are in the same category (Industry): 25 approved, 10 filed or under review, and 5 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 24 acres, this one is larger than 55% of them.

12 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Bobbili, Vizianagaram, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Hira Electro Smelters Limited in Vizianagaram

All 6 Hira Electro Smelters projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.