What is this project?
2.595 Hectares of Lime Stone Slabs(Black) Quarry of Sri S. Rameswara Reddy,Sy.No.707 of Cherlopalli Village, Owk Mandal, Kurnool District, A.P is a lapsed mining project in Cherlapalle, Owk, Nandyal, Andhra Pradesh. The site covers 6.4 acres.
Who is building it?
The applicant is Sunkari Reddy.
Has it been approved?
No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.
Where is it?
In Cherlapalle, Owk, Nandyal, Andhra Pradesh.
How big is it?
It has a stated cost of ₹30 lakh and a site of 6.4 acres.
When was it filed?
The application was filed on 23 Mar 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 29 Oct 2024 |
| Application filed | 23 Mar 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Sunkari Reddy |
| Land area | 6.4 acres (2.6 ha) |
| Project cost | ₹30 lakh |
| Village / locality | Cherlapalle |
| Taluk / tehsil | Owk |
| District | Nandyal |
| State | Andhra Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AP-01957 |
In context
135 applications in Nandyal since January 2022 are in the same category (Mining): 80 approved, 16 filed or under review, and 39 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 6.4 acres, this one is smaller than 67% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 25.8 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 1 mining lease has applied within 5 km.
Where it is
Cherlapalle, Owk, Nandyal, Andhra Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Mining project by M/s Muslim Minority Welfare Society — environmental approval granted, 200 m away
- AMENDMENT IN CONSENT TO ESTABLISHMENT CHANGE IN CONFIGURATION OF CEMENT PLANT… — initial checks, 8.1 km away
- Expansion of Cement Plant (Clinker from 3.15 MTPA to 6.3 MTPA, Cement from 2.0… — environmental approval granted, 8.1 km away
- Enhancement in Cement production (Line-I) from 2.0 MTPA to 2.4 MTPA, with no… — initial checks, 8.1 km away
- Amendment to the Environmental Clearance (Ec) for Specific Condition No III of… — environmental approval granted, 8.1 km away
- Expansion of Cement Plant (Clinker from 3.15 MTPA to 6.3 MTPA, Cement from 2.0… — cleared for impact study, 8.1 km away
- Expansion of Cement Plant (Clinker from 3.15 MTPA to 6.3 MTPA, Cement from 2.0… — withdrawn, 8.1 km away
- Validity Extension of Environment Clearance Letter no. J-11015/243/2008-IA.II… — environmental approval granted, 8.5 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.