Quick answers
What is Forest Clearance?
Forest Clearance is a lapsed project in Maliney, Etalin, Upper Dibang Valley, Arunachal Pradesh. The site covers 13,774.3 acres.
Who is building it?
The applicant is Ministry of Defense.
Has it been approved?
No. The application was lapsed on 25 Jun 2024, so it is no longer under consideration.
Where is it?
In Maliney, Etalin, Upper Dibang Valley, Arunachal Pradesh.
How big is it?
It has a stated cost of ₹50 lakh; a site of 13,774.3 acres and 6.5 acres (2.6 ha) of forest land.
When was it filed?
The application was filed on 9 Dec 2023.
Project details
| Status | Lapsed |
|---|---|
| Status since | 25 Jun 2024 |
| Application filed | 9 Dec 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Other |
| Applicant | Ministry of Defense |
| Land area | 13,774.3 acres (5,574.3 ha) |
| Forest land | 6.5 acres (2.6 ha) |
| Project cost | ₹50 lakh |
| Village / locality | Maliney |
| Taluk / tehsil | Etalin |
| District | Upper Dibang Valley |
| State | Arunachal Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-AR-00192 |
In context
9 applications in Upper Dibang Valley since January 2022 are in the same category (Other): 0 approved, 5 filed or under review, and 3 withdrawn, lapsed or rejected.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Maliney, Etalin, Upper Dibang Valley, Arunachal Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of 0.6 Hact. of Forest Land for Construction of New Staging Camp… — decision issued, 650 m away
- Diversion of 0.6 Hac. of Forest land for establishment of New Staging camp at… — decision issued, 8.5 km away
- Attunli Hydroelectric Project (680 MW) — environmental approval granted, 12.7 km away
- Attunli Hydro Electric Project — in-principle approval, conditions pending, 12.7 km away
- Attunli Hydroelectric Project (680 MW) — cleared for impact study, 12.7 km away
- Wildlife Clearance Proposal for Construction of Malinye-Balua-Kapuda Road From… — decision issued, 12.7 km away
- Wildlife Clearance Proposal for Construction of Malinye-Balua-Kapuda Road From… — more information requested, 12.7 km away
- Wildlife Clearance Proposal for Construction of Malinye-Balua-Kapuda Road From… — more information requested, 14.2 km away
More from Ministry of Defense in Upper Dibang Valley
- Establishment of New Amn Shelters & Gun Position - Bruni — lapsed
- Establishment of New Amn Shelters & Gun Position - Bruni — more information requested
- Preparation of Gun Area and Construction of Ammunition Shelters at Bruni (Near… — more information requested
- Establishment of New Amn Shelter & Gun Position - Bruni — under wildlife review
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.