One of 2 filings for this project. The project's main page, with every filing and where each stands: Sand Mining Project at Block No. 10 on Kiul River of District - Lakhisarai over area…
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 30 Nov 2022 |
| Application filed | 30 Nov 2022 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Amit Singh |
| Land area | 97.1 acres (39.3 ha) |
| Project cost | ₹13.7 crore |
| Village / locality | Nongarh |
| Taluk / tehsil | Ramgarh Chowk |
| District | Lakhisarai |
| State | Bihar |
| Location from | Site boundary on record |
| Our reference | WID-BR-00044 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 14 Aug 2023 | Environmental approval granted | 97.1 acres | ₹13.7 crore |
| Early planning filed 30 Nov 2022 (this page) | Cleared for impact study | 97.1 acres | ₹13.7 crore |
In context
38 applications in Lakhisarai since January 2022 are in the same category (Mining): 33 approved, 1 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 97.1 acres, this one is larger than 79% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 176.2 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 7 mining leases have applied within 5 km.
Where it is
Nongarh, Ramgarh Chowk, Lakhisarai, Bihar. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Sand Mining Project at Block No. 10 on Kiul River of District - Lakhisarai… — environmental approval granted, 0 m away
- Sand Mining Project at Kiul River Cluster II (Block No.- 11 & 12) Lakhisarai… — environmental approval granted, 450 m away
- Sand Mining Project at Kiul River Cluster II (Block No.- 11 & 12) Lakhisarai… — cleared for impact study, 450 m away
- Sand Ghat Mining Project (Lakhisarai Block No.- 09) at Riverbed of Kiul River — environmental approval granted, 1 km away
- Sand Ghat Mining Project (Lakhisarai Block No.- 09) at Riverbed of Kiul River — cleared for impact study, 1 km away
- Sand Mining Project Kiul Block no.-12 Sand Ghat — cleared for impact study, 1.7 km away
- Proposed Sand Mining Project of Area 33.2 Ha at Lakhisarai Kiul-08 Ghat on… — environmental approval granted, 1.7 km away
- Proposed Sand Mining Project of Area 33.2 Ha at Lakhisarai Kiul-08 Ghat on… — cleared for impact study, 1.7 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.