What is Developing? Open the mapMap

Cleared for impact studyMining · Gaya, Bihar

Sand Mining Project, Block 40 (Gaya Budh 04/05/06/07/ 08) Sand Ghat

Sand Mining Project, Block 40 (Gaya Budh 04/05/06/07/ 08) Sand Ghat is a proposed mining project in Kareya, Tikari, Gaya, Bihar. The site covers 161.9 acres. Its stated project cost is ₹10.7 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 20 Apr 2023).

See it on the live map All projects in Gaya

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Sand Mining Project, Block 40 (Gaya Budh 04/05/06/07/ 08) Sand Ghat is a proposed mining project in Kareya, Tikari, Gaya, Bihar. The site covers 161.9 acres.

Who is building it?

The applicant is Dashmesh Contractors.

Has it been approved?

Yes. Its status is “Cleared for impact study” (since 20 Apr 2023), as of 27 Nov 2026.

Where is it?

In Kareya, Tikari, Gaya, Bihar.

How big is it?

It has a stated cost of ₹10.7 crore and a site of 161.9 acres.

When was it filed?

The application was filed on 20 Apr 2023.

One of 2 filings for this project. The project's main page, with every filing and where each stands: Sand Mining Project, Block 40 (Gaya Budh 04/05/06/07/ 08) Sand Ghat

Project details

StatusCleared for impact study
Status since20 Apr 2023
Application filed20 Apr 2023
Approval soughtEnvironmental approval
Application typeEarly planning
SectorMining
ApplicantDashmesh Contractors
Land area161.9 acres (65.5 ha)
Project cost₹10.7 crore
Village / localityKareya
Taluk / tehsilTikari
DistrictGaya
StateBihar
Location fromSite boundary on record
Our referenceWID-BR-00420

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 8 Nov 2023Environmental approval granted161.9 acres₹10.7 crore
Early planning filed 20 Apr 2023 (this page)Cleared for impact study161.9 acres₹10.7 crore

In context

189 applications in Gaya since January 2022 are in the same category (Mining): 171 approved, 15 filed or under review, and 3 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 161.9 acres, this one is larger than 99% of them.

No other mining lease on record is within 500 m of this site; 5 have applied within 5 km.

Where it is

Kareya, Tikari, Gaya, Bihar. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.