What is this project?
Greenfield steel plant comprising of Iron ore beneficiation (8,50,000 TPA), Pellet Plant (6,00,000 TPA), Gasifier for Pellet Plant (21,000 Nm3/hr) DRI Kilns (6,27,000 TPA), Induction Furnace with matching LRF & CCM (Hot Billets / Billets / Ingots - 4,62,000 TPA), Rolling Mill (TMT Bars / Structural Steel - 4,62,000 TPA),Gasifier for Reheating Furnace (3570 Nm3/hr), Ferro Alloy Unit (FeSi – 42,000 TPA/FeMn – 1,51,200 TPA/SiMn – 86,400 TPA/FeCr – 90,000 TPA/Pig Iron – 60,000 TPA) is an approved industrial project in Jhiria, Bemetara, Bametara, Chhattisgarh. The site covers 107.6 acres.
Who is building it?
The applicant is Navic Steel and Power Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 23 Jun 2025), as of 27 Nov 2026.
Where is it?
In Jhiria, Bemetara, Bametara, Chhattisgarh.
How big is it?
It has a stated cost of ₹850 crore and a site of 107.6 acres.
When was it filed?
The application was filed on 30 Jan 2024.
Project details
| Official title | Establishment of Greenfield steel plant comprising of Iron ore beneficiation (8,50,000 TPA), Pellet Plant (6,00,000 TPA), Gasifier for Pellet Plant (21,000 Nm3/hr) DRI Kilns (6,27,000 TPA), Induction Furnace with matching LRF & CCM (Hot Billets / Billets / Ingots - 4,62,000 TPA), Rolling Mill (TMT Bars / Structural Steel - 4,62,000 TPA),Gasifier for Reheating Furnace (3570 Nm3/hr), Ferro Alloy Unit (FeSi – 42,000 TPA/FeMn – 1,51,200 TPA/SiMn – 86,400 TPA/FeCr – 90,000 TPA/Pig Iron – 60,000 TPA) |
|---|---|
| Status | Environmental approval granted |
| Status since | 23 Jun 2025 |
| Application filed | 30 Jan 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Navic Steel and Power Private Limited |
| Land area | 107.6 acres (43.6 ha) |
| Project cost | ₹850 crore |
| Village / locality | Jhiria |
| Taluk / tehsil | Bemetara |
| District | Bametara |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-00533 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Early planning filed 9 Feb 2024 | Withdrawn | 107.6 acres | ₹850 crore |
| New project filed 30 Jan 2024 (this page) | Environmental approval granted | 107.6 acres | ₹850 crore |
In context
24 applications in Bametara since January 2022 are in the same category (Industry): 15 approved, 3 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 107.6 acres, this one is larger than 75% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Jhiria, Bemetara, Bametara, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Greenfield steel plant comprising of Iron ore beneficiation (8,50,000 TPA),… — withdrawn, 0 m away
- Proposed 100 KLPD Fuel Ethanol Unit by using Grain as Feed Stock — environmental approval granted, 3.9 km away
- Increase in Bio Ethanol and Bye Product Production Due to Proposed Improvement… — initial checks, 7.7 km away
- Dokla Bricks Earth Quarry — environmental approval granted, 14.6 km away
- Request for Amendment to Environmental Clearance (EC) issued to BIOTECH FUELS… — environmental approval granted, 16.1 km away
- Proposed "enhancement in Ethanol (Grain based) Production Capacity from 65… — initial checks, 16.1 km away
- Grain Based Distllery Palnt Capacity of 1 X 65 Klpd — environmental approval granted, 16.1 km away
- Brick Earth Quarry — environmental approval granted, 18.2 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.