Environmental approval grantedIndustry · Durg, Chhattisgarh

Proposed Capacity Expansion of Sponge Iron (97,500 TPA to 140,000 TPA); MS Billet (90,000 TPA to 192,500 TPA); Rerolled Steel Products (90,000 TPA to 180,000 TPA -: Through Hot Charging 126000 TPA and through Reheating Furnace 54,000 TPA); Existing Captive Power 8 MW (through WHRB); and Pipe Mill 175,000 TPA (new) within existing plant premises located at Plot No: 14-A, Heavy Industrial Area, Hathkhoj, Bhilai, Dist.- Durg (C.G.) Pin code 490026 by M/s. Niros Ispat Private Limited

Proposed Capacity Expansion of Sponge Iron (97,500 TPA to 140,000 TPA); MS Billet (90,000 TPA to 192,500 TPA); Rerolled Steel Products (90,000 TPA to 180,000 TPA -: Through Hot Charging 126000 TPA and through Reheating Furnace 54,000 TPA); Existing Captive Power 8 MW (through WHRB); and Pipe Mill 175,000 TPA (new) within existing plant premises located at Plot No: 14-A, Heavy Industrial Area, Hathkhoj, Bhilai, Dist.- Durg (C.G.) Pin code 490026 by M/s. Niros Ispat Private Limited is an approved industrial project in Hathkhoj, Durg, Chhattisgarh. The site covers 22 acres. Its stated project cost is ₹182.6 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 16 Oct 2023).

See it on the live map All projects in Durg

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

StatusEnvironmental approval granted
Status since16 Oct 2023
Application filed19 Aug 2023
Approval soughtEnvironmental approval
Application typeExpansion
SectorIndustry
ApplicantNiros Ispat PVT LTD
Land area22 acres (8.9 ha)
Project cost₹182.6 crore
Village / localityHathkhoj
Taluk / tehsilDurg
DistrictDurg
StateChhattisgarh
Location fromSite boundary on record
Our referenceWID-CG-00718

In context

41 applications in Durg since January 2022 are in the same category (Industry): 25 approved, 13 filed or under review, and 3 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 22 acres, this one is larger than 59% of them.

20 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Hathkhoj, Durg, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.