What is this project?
Expansion of Steel Plant – DRI Kilns (Sponge Iron from 60,000TPA to 2,40,000 TPA), WHRB based Power Plant from 4 MW to 16 MW, AFBCbased Power Plant from 8 MW to 14MW, SEAF 1x4 MVA (Cast Iron -15,000 TPA), SEAFs 2x9 MVA (FeSi – 14,000 TPA / FeMn-50,400 TPA / SiMn-28,800 TPA / FeCr-30,000 TPA.) Establishment of New Induction Furnaces is an approved industrial project in Bare Gumda, Gharghoda, Raigarh, Chhattisgarh. The site covers 43.1 acres.
Who is building it?
The applicant is Sun Steel & Power Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 25 Jul 2025), as of 27 Nov 2026.
Where is it?
In Bare Gumda, Gharghoda, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹633 crore and a site of 43.1 acres.
When was it filed?
The application was filed on 28 Apr 2025.
Project details
| Official title | Expansion of Steel Plant – DRI Kilns (Sponge Iron from 60,000TPA to 2,40,000 TPA), WHRB based Power Plant from 4 MW to 16 MW, AFBCbased Power Plant from 8 MW to 14MW, SEAF 1x4 MVA (Cast Iron -15,000 TPA), SEAFs 2x9 MVA (FeSi – 14,000 TPA / FeMn-50,400 TPA / SiMn-28,800 TPA / FeCr-30,000 TPA.) Establishment of New Induction Furnaces along with CCM&LRF (Hot Billets / Billets / Ingots 1,80,000 TPA), Rolling Mill (TMT bars / Wire Rods)(85 % Hot charging with Hot Billets and remaining 15% through R |
|---|---|
| Status | Environmental approval granted |
| Status since | 25 Jul 2025 |
| Application filed | 28 Apr 2025 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Sun Steel & Power Private Limited |
| Land area | 43.1 acres (17.4 ha) |
| Project cost | ₹633 crore |
| Village / locality | Bare Gumda |
| Taluk / tehsil | Gharghoda |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-00972 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 28 Apr 2025 (this page) | Environmental approval granted | 43.1 acres | ₹633 crore |
| Early planning filed 5 Aug 2023 | Cleared for impact study | 43.1 acres | ₹633 crore |
In context
113 applications in Raigarh since January 2022 are in the same category (Industry): 64 approved, 28 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 43.1 acres, this one is smaller than 69% of them.
7 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bare Gumda, Gharghoda, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Steel Plant – DRI Kilns (Sponge Iron from 60,000TPA to 2,40,000… — cleared for impact study, 0 m away
- Coal Washery and Railway Siding — lapsed, 1.2 km away
- Railway Siding — more information requested, 1.3 km away
- Railway Siding — lapsed, 1.3 km away
- Submerged Electric Arc Furnaces -2x 9 MVA (Fesi-14,000TPA / FeMn-40,000 TPA /… — cleared for impact study, 2.7 km away
- Greenfield Steel Project-Nawapara Unit-I/O Pellets(1.2MTPA)+PGP(30000NM3/Hr),Sp… — under environmental review, 4.9 km away
- Greenfield Steel Project-Nawapara Unit-I/O Pellets(1.2MTPA)+PGP(30000NM3/Hr),Sp… — cleared for impact study, 4.9 km away
- Greenfield Steel Project-Nawapara Unit-I/O Pellets(1.2MTPA)+PGP(30000NM3/Hr),Sp… — cleared for impact study, 4.9 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.