Quick answers
What is this project?
Capacity enhancement of Rolling Mill from 100000 TPA to 135000 TPA is a proposed industrial project in Barpali, Tamnar, Raigarh, Chhattisgarh. The site covers 46.1 acres.
Who is building it?
The applicant is Nav Durga Fuel Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Barpali, Tamnar, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹63 crore and a site of 46.1 acres.
When was it filed?
The application was filed on 7 Sept 2024.
Project details
| Status | Initial checks |
|---|---|
| Status since | 7 Sept 2024 |
| Application filed | 7 Sept 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Nav Durga Fuel Private Limited |
| Land area | 46.1 acres (18.7 ha) |
| Project cost | ₹63 crore |
| Village / locality | Barpali |
| Taluk / tehsil | Tamnar |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-01119 |
In context
113 applications in Raigarh since January 2022 are in the same category (Industry): 64 approved, 28 filed or under review, and 21 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 46.1 acres, this one is smaller than 64% of them.
16 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Barpali, Tamnar, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Expansion of existing steel plant by increasing of existing Sponge… — more information requested, 0 m away
- Proposed Expansion of existing steel plant by increasing of existing Sponge… — returned to applicant, 0 m away
- Amendment in Environmental Clearance for 100 KLPD Grain Based Ethanol Plant by… — more information requested, 400 m away
- Expansion of Steel Plant – DRI Kilns (Sponge Iron from 1,20,000 TPA to… — environmental approval granted, 750 m away
- Splitting of EC facilities issued to M/s. Shree Rupanadham Steel Pvt. Ltd.… — under environmental review, 750 m away
- Proposed expansion by Installation of Production Facilities for: Sponge Iron… — initial checks, 1.1 km away
- Proposed expansion by Installation of Production Facilities for: Sponge Iron… — environmental approval granted, 1.1 km away
- Proposed expansion by Installation of Production Facilities for: Sponge Iron… — cleared for impact study, 1.1 km away
More from Nav Durga Fuel Private Limited in Raigarh
- Proposed Expansion of existing steel plant by increasing of existing Sponge… — more information requested
- Amendment in Environmental Clearance for 100 KLPD Grain Based Ethanol Plant by… — more information requested
- Proposed Expansion of existing steel plant by increasing of existing Sponge… — returned to applicant
4 Nav Durga Fuel projects in Raigarh
All 5 Nav Durga Fuel projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.