Quick answers
What is this project?
Greenfield Steel Plant by PERA MINING INDUSTRIES LLP--- I/O Beneficiation Plant-2.4 MTPA, Pellet Plant-1.8 MTPA, Sponge Iron- 11,88,000 TPA, Hot Billets/Ingots (EAF)-10,29,600 TPA, Rolling Mill-(Strip mill, Structural Mill, TMT mill), PGP-5 x 6500 Nm3/hr, PCI Unit–1 x 5 TPH, SEAFs of 2 x 9 MVA (FeSi/ FeMn/SiMn/FeCr/Pig Iron), Briquetting Plant-200 kg/hr, WHRB–6x18 MW, CFBC–2x50 MW, Fly Ash Brick-1,00,000 Bricks/Day is a proposed industrial project in Barda, Dondi Luhara, Balod, Chhattisgarh. The site covers 104.1 acres.
Who is building it?
The applicant is Pera Mining Industries LLP.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 16 Jun 2026), as of 27 Nov 2026.
Where is it?
In Barda, Dondi Luhara, Balod, Chhattisgarh.
How big is it?
It has a stated cost of ₹490 crore and a site of 104.1 acres.
When was it filed?
The application was filed on 4 Feb 2026.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 16 Jun 2026 |
| Application filed | 4 Feb 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Pera Mining Industries LLP |
| Land area | 104.1 acres (42.1 ha) |
| Project cost | ₹490 crore |
| Village / locality | Barda |
| Taluk / tehsil | Dondi Luhara |
| District | Balod |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-03321 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 21 Nov 2026 | Under environmental review | 136.1 acres | ₹3,527 crore |
| Early planning filed 4 Feb 2026 (this page) | Cleared for impact study | 104.1 acres | ₹490 crore |
In context
6 applications in Balod since January 2022 are in the same category (Industry): 3 approved, 2 filed or under review, and 1 withdrawn, lapsed or rejected.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Barda, Dondi Luhara, Balod, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Chhedilal chakradhari Bricks Earth Mine Area 3.81 Hec. — environmental approval granted, 50 m away
- Greenfield steel plant comprising of I/O Beneficiation Plant-2.4 MTPA… — withdrawn, 7.9 km away
- Ujiyar Singh Pawar — lapsed, 9.1 km away
- M/s Laxmi Devi Godwani Brick Earth Mine — environmental approval granted, 10.3 km away
- Steel plant comprising of I/O Beneficiation Plant-2.4 MTPA (throughput),… — withdrawn, 13.5 km away
- Shri Anil Kumar Chawda, Limora Bricks Earth Clay Mine Area 1.60hec. — initial checks, 15 km away
- Limora Bricks Earth Clay Mine Area 1.38 Hec. — environmental approval granted, 15.5 km away
- Greenfield Steel Plant by PERA MINING INDUSTRIES LLP--- I/O Beneficiation… — under environmental review, 16 km away
More from Pera Mining Industries LLP in Balod
- Greenfield Steel Plant - I/O Beneficiation Plant-2.4 MTPA, Pellet Plant-1.8… — returned to applicant
- Greenfield steel plant comprising of I/O Beneficiation Plant-2.4 MTPA… — withdrawn
- Steel plant comprising of I/O Beneficiation Plant-2.4 MTPA (throughput),… — withdrawn
All 5 Pera Mining Industries projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.