Quick answers
What is this project?
Greenfield project comprising of Iron ore Beneficiation Plant – 1.2 MTPA, Pelletization Plant - 0.9 MTPA is a proposed industrial project in Gudum, Dondi, Balod, Chhattisgarh. The site covers 98.1 acres.
Who is building it?
The applicant is Mineral Dynamics Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 22 May 2026), as of 27 Nov 2026.
Where is it?
In Gudum, Dondi, Balod, Chhattisgarh.
How big is it?
It has a stated cost of ₹340 crore and a site of 98.1 acres.
When was it filed?
The application was filed on 20 Feb 2026.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Greenfield project comprising of Iron ore Beneficiation Plant – 1.2 MTPA, Pelletization…
Project details
| Official title | Establishment of Greenfield project comprising of Iron ore Beneficiation Plant – 1.2 MTPA, Pelletization Plant - 0.9 MTPA along with Producer Gas Plant – 6 x 4000 Nm3/Hr., Submerged Electric Arc Furnace - 1 x 5 MVA (FeSi - 4,616 TPA / FeMn - 12,782 TPA / SiMn - 8,875 TPA / FeCr - 9,232 TPA/ Pig Iron - 16,329 TPA), Jigging unit – 2 TPH, Briquetting Plant - 55 Kg/Hr., Brick Manufacturing unit - 10,000 Bricks / Day |
|---|---|
| Status | Cleared for impact study |
| Status since | 22 May 2026 |
| Application filed | 20 Feb 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Mineral Dynamics Private Limited |
| Land area | 98.1 acres (39.7 ha) |
| Project cost | ₹340 crore |
| Village / locality | Gudum |
| Taluk / tehsil | Dondi |
| District | Balod |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-03682 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 9 Sept 2026 | Environmental approval granted | 76.2 acres | ₹340 crore |
| Early planning filed 20 Feb 2026 (this page) | Cleared for impact study | 98.1 acres | ₹340 crore |
In context
6 applications in Balod since January 2022 are in the same category (Industry): 3 approved, 2 filed or under review, and 1 withdrawn, lapsed or rejected.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Gudum, Dondi, Balod, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Ghotiya Sand Quarry 3.76H — initial checks, 1.6 km away
- Ghotiya Sand Quarry — environmental approval granted, 1.6 km away
- Singhanwahi Sand Mines — lapsed, 3.1 km away
- Preliminary Exploration Survey (G-3 Stage) for Iron Ore in the… — not approved, 8.3 km away
- Environment Clearance of Pandridalli & Rajhara Pahar Iron Ore Lease (ML Area… — environmental approval granted, 9.1 km away
- Greenfield project comprising of Iron ore Beneficiation Plant – 1.2 MTPA,… — environmental approval granted, 13.1 km away
- Environmental Clearance granted for Iron Ore Crushing, Screening and… — environmental approval granted, 14 km away
- Expansion in Final Product (Iron Ore Pellets) Capacity up to 40% in Two Phases… — under environmental review, 14.3 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.