Diversion of forest land for non-forest purpose under Forest Conservation Act, 1980 for Construction of 220KV DCSS Transmission Line from CSPTCL 220/132/33 KV S/S Gerwani to Switchyard of upcomming solar power Plant of M/S Godawari Energy Limited is a lapsed power project in Traimal, Tamnar, Raigarh, Chhattisgarh. The site covers 916 acres.
Who is building it?
The applicant is Godawari Energy Limited.
Has it been approved?
No. The application was lapsed on 14 Jul 2026, so it is no longer under consideration.
Where is it?
In Traimal, Tamnar, Raigarh, Chhattisgarh.
How big is it?
It has a stated cost of ₹3 crore; a site of 916 acres and 32.7 acres (13.2 ha) of forest land.
When was it filed?
The application was filed on 28 Mar 2026.
Project details
| Official title | Diversion of forest land for non-forest purpose under Forest Conservation Act, 1980 for Construction of 220KV DCSS Transmission Line from CSPTCL 220/132/33 KV S/S Gerwani to Switchyard of upcomming solar power Plant of M/S Godawari Energy Limited, At Village- Bojia (Chhal). |
|---|---|
| Status | Lapsed |
| Status since | 14 Jul 2026 |
| Application filed | 28 Mar 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Godawari Energy Limited |
| Land area | 916 acres (370.7 ha) |
| Forest land | 32.7 acres (13.2 ha) |
| Project cost | ₹3 crore |
| Village / locality | Traimal |
| Taluk / tehsil | Tamnar |
| District | Raigarh |
| State | Chhattisgarh |
| Location from | Site boundary on record |
| Our reference | WID-CG-04173 |
In context
29 applications in Raigarh since January 2022 are in the same category (Power): 13 approved, 9 filed or under review, and 7 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 916 acres, this one is larger than 68% of them.
Where it is
Traimal, Tamnar, Raigarh, Chhattisgarh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Amendment in Environmental Clearance for 100 KLPD Grain Based Ethanol Plant by… — more information requested, 5.5 km away
- Proposed expansion by Installation of Production Facilities for: Sponge Iron… — initial checks, 5.7 km away
- Proposed expansion by Installation of Production Facilities for: Sponge Iron… — environmental approval granted, 5.7 km away
- Proposed expansion by Installation of Production Facilities for: Sponge Iron… — cleared for impact study, 5.7 km away
- Capacity enhancement of Rolling Mill from 100000 TPA to 135000 TPA — initial checks, 5.8 km away
- Proposed Expansion of existing steel plant by increasing of existing Sponge… — more information requested, 5.9 km away
- Proposed Expansion of existing steel plant by increasing of existing Sponge… — returned to applicant, 5.9 km away
- Industrial project by Shri Dayal Industries Pvt. Ltd. — more information requested, 6 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.