Quick answers
What is this project?
Estimate for Work of Electrification of Left-Out Wada at Keri, Under Vp Cotigao of Canacona Taluka is an approved power project in Cotigao, Canacona, South Goa, Goa. The site covers 11.3 acres.
Who is building it?
The applicant is Office of the Executive Engineer Division Xvi Electricity Department.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 22 Oct 2026), as of 27 Nov 2026.
Where is it?
In Cotigao, Canacona, South Goa, Goa.
How big is it?
It has a stated cost of ₹3.7 crore; a site of 11.3 acres and 3,420 m² of forest land.
When was it filed?
The application was filed on 23 Sept 2024.
Project details
| Official title | Estimate for Work of Electrification of Left-Out Wada at Keri, Under Vp Cotigao of Canacona Taluka Under the Jurisdiction of Sub Division-Iii Canacona, Div-Xvi, Margao. |
|---|---|
| Status | Forest land use approved |
| Status since | 22 Oct 2026 |
| Application filed | 23 Sept 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Office of the Executive Engineer Division Xvi Electricity Department |
| Land area | 11.3 acres (4.6 ha) |
| Forest land | 3,420 m² |
| Project cost | ₹3.7 crore |
| Village / locality | Cotigao |
| Taluk / tehsil | Canacona |
| District | South Goa |
| State | Goa |
| Location from | Site boundary on record |
| Our reference | WID-GA-00285 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 23 Sept 2024 (this page) | Forest land use approved | 11.3 acres | ₹3.7 crore |
| New project filed 23 Sept 2024 | Decision issued | 11.3 acres | ₹3.7 crore |
In context
8 applications in South Goa since January 2022 are in the same category (Power): 2 approved, 4 filed or under review, and 0 withdrawn, lapsed or rejected.
7 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Cotigao, Canacona, South Goa, Goa. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Estimate for Work of Electrification of Left-Out Wada at Keri, Under Vp… — decision issued, 0 m away
- Forest Land Diversion for Reconstruction of Existing Kuccha Road — decision issued, 250 m away
- Forest Land Diversion for Reconstruction of Existing Kuccha Road — lapsed, 250 m away
- Forest Land Diversion for Reconstruction of Existing Kuccha Road — more information requested, 800 m away
- Forest Land Diversion for Reconstruction of Existing Kuccha Road — more information requested, 800 m away
- GOI USOF BSNL 4G Saturation Project at Kuske-Yeda — forest land use approved, 1.2 km away
- Laying of underground Optical Fiber Cable for connecting the 4G Mobile Tower — initial checks, 2.1 km away
- Development of Monem Tank in V.P Cotigao Canacona Taluka — lapsed, 4.6 km away
More from Office of the Executive Engineer Division Xvi Electricity Department in South Goa
- Conversion of 11KV Overhead network of Marli Tirwal Feeder to Underground HT… — in-principle approval, conditions pending
- Conversion of 11KV Overhead network of Marli Tirwal Feeder to Underground HT… — lapsed
- Conversion of 11KV Overhead network of Marli Tirwal Feeder to Underground HT… — decision issued
All 5 Office of the Executive Engineer Division Xvi Electricity Department projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.