What is Developing? Open the mapMap

WithdrawnBuildings & townships · Valsad, Gujarat

Residential Cum Commercial Project – "marina Bay" at Block/Survey No.: 1193 (Old Block/Survey No. 533/1), Moje: Umarsadi, Tal.: Pardi, Dist.: Valsad, Gujarat-396125 by Mr. Rutvik Jignesh Desai

Residential Cum Commercial Project – "marina Bay" at Block/Survey No.: 1193 (Old Block/Survey No. 533/1), Moje: Umarsadi, Tal.: Pardi, Dist.: Valsad, Gujarat-396125 by Mr. Rutvik Jignesh Desai is a withdrawn building project in Umarsadi, Pardi, Valsad, Gujarat. The site covers 8.2 acres. Its stated project cost is ₹66.4 crore. As of 27 Nov 2026, its status is “Withdrawn” (since 21 May 2025).

See it on the live map All projects in Valsad

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Residential Cum Commercial Project – "marina Bay" at Block/Survey No.: 1193 (Old Block/Survey No. 533/1), Moje: Umarsadi, Tal.: Pardi, Dist.: Valsad, Gujarat-396125 by Mr. Rutvik Jignesh Desai is a withdrawn building project in Umarsadi, Pardi, Valsad, Gujarat. The site covers 8.2 acres.

Who is building it?

The applicant is Desai Rutvik.

Has it been approved?

No. The application was withdrawn on 21 May 2025, so it is no longer under consideration.

Where is it?

In Umarsadi, Pardi, Valsad, Gujarat.

How big is it?

It has a stated cost of ₹66.4 crore and a site of 8.2 acres.

When was it filed?

The application was filed on 28 Nov 2024.

One of 2 filings for this project. The project's main page, with every filing and where each stands: Residential Cum Commercial Project – "marina Bay" at Block/Survey No.: 1193 (Old…

Project details

Official titleProposed Construction of Residential Cum Commercial Project – "marina Bay" at Block/Survey No.: 1193 (Old Block/Survey No. 533/1), Moje: Umarsadi, Tal.: Pardi, Dist.: Valsad, Gujarat-396125 by Mr. Rutvik Jignesh Desai.
StatusWithdrawn
Status since21 May 2025
Application filed28 Nov 2024
Approval soughtEnvironmental approval
Application typeNew project
SectorBuildings & townships
ApplicantDesai Rutvik
UseOther
Land area8.2 acres (3.3 ha)
Project cost₹66.4 crore
Village / localityUmarsadi
Taluk / tehsilPardi
DistrictValsad
StateGujarat
Location fromSite boundary on record
Our referenceWID-GJ-02485

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 9 Jan 2025Returned to applicant8.2 acres₹66.4 crore
New project filed 28 Nov 2024 (this page)Withdrawn8.2 acres₹66.4 crore

What the filings say

What is planned

Mr. Rutvik Jignesh Desai proposes the construction of "Marina Bay," a residential-cum-commercial project in Umarsadi, Valsad. The applicant's project report describes a development consisting of 108 flats, 129 bungalows, and 40 commercial shops, along with a society office and multipurpose hall.

The residential component is divided into several building types:

ItemDetail
Total Plot Area33,202.00 sq. m.
Total Built-up Area35,643.78 sq. m.
FSI Area30,031.07 sq. m.
Total Residential Units237 (108 Flats + 129 Bungalows)
Total Commercial Units40 Shops
Total Parking Area7,486.04 sq. m.
Estimated Project Cost₹66.6 crore

Land and surroundings

The project site is located on 3.32 hectares (8.20 acres) of private non-agricultural land. It is situated adjacent to the Par River and the Coastal Highway. The applicant states that the site partly falls within Coastal Regulation Zone (CRZ) categories CRZ IA (50m mangrove buffer zone), CRZ IB, and CRZ II, with the remaining area outside the CRZ. The proposed buildings are planned completely inside the 'Port Limit'.

Surrounding landmarks include the Umarsadi Beach (1.24 km west) and the Arabian Sea (1.69 km west). No national parks or wildlife sanctuaries are located within a 10 km radius, though the Parnera Hill reserved forest is 5.6 km to the northeast.

Water, power and access

During the operational phase, the total water requirement is estimated at 239.0 KLD. Fresh water (109.0 KLD) will be sourced from the Umarsadi-Machhiwad Gram Panchayat, while the remaining 130.0 KLD will be met through recycled water. A Sewage Treatment Plant (STP) with a capacity of 170.0 KLD is proposed to treat domestic wastewater. Treated water will be reused for flushing, vehicle washing, and gardening.

Power will be supplied by Dakshin Gujarat Vij Company Limited (DGVCL), with a total operational requirement of 1,910 KWH. Two diesel generator sets of 500 KVA each are planned for backup. The project also includes 172 KW of rooftop solar installations covering 8,268.05 sq. m. of terrace space.

Environmental safeguards

The applicant proposes a greenbelt covering 10,958.0 sq. m. (approximately 33% of the plot area), which will include the planting of 2,291 trees. For solid waste management, an organic waste converter with a capacity of 400 kg/day will process biodegradable waste into manure for use on-site. Non-biodegradable waste will be collected and disposed of as per municipal rules. Rainwater harvesting will be managed through a collection system and nine recharge wells.

Timeline

The project implementation schedule estimates a total construction period of approximately 33 months from the start of work. Key phases include:

Mr. Rutvik Jignesh Desai Residential Cum Commercial Project – "marina Bay" site plan and layout

4 drawings from the project's filings. Sign in free to see them.

Mr. Rutvik Jignesh Desai Residential Cum Commercial Project – "marina Bay": Master layout plan: residential blocks, bungalows, roads, and greenbelt (preview)🔒 Sign in free to see it
Master layout plan: residential blocks, bungalows, roads, and greenbelt
Mr. Rutvik Jignesh Desai Residential Cum Commercial Project – "marina Bay": Site plan showing building footprints and internal road network (preview)🔒 Sign in free to see it
Site plan showing building footprints and internal road network
Mr. Rutvik Jignesh Desai Residential Cum Commercial Project – "marina Bay": Key plan showing project location and surrounding survey numbers (preview)🔒 Sign in free to see it
Key plan showing project location and surrounding survey numbers
Mr. Rutvik Jignesh Desai Residential Cum Commercial Project – "marina Bay": Elevation and sectional drawing of A-type residential blocks (preview)🔒 Sign in free to see it
Elevation and sectional drawing of A-type residential blocks

In context

64 applications in Valsad since January 2022 are in the same category (Buildings & townships): 46 approved, 10 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 8.2 acres, this one is larger than 73% of them.

2 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Umarsadi, Pardi, Valsad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.