Quick answers
What is this project?
Residential Cum Commercial Project – "marina Bay" at Block/Survey No.: 1193 (Old Block/Survey No. 533/1), Moje: Umarsadi, Tal.: Pardi, Dist.: Valsad, Gujarat-396125 by Mr. Rutvik Jignesh Desai is a proposed building project in Umarsadi, Pardi, Valsad, Gujarat. The site covers 8.2 acres.
Who is building it?
The applicant is Desai Rutvik.
Has it been approved?
Not yet. The application is still under review: its status is “Returned to applicant”, as of 27 Nov 2026.
Where is it?
In Umarsadi, Pardi, Valsad, Gujarat.
How big is it?
It has a stated cost of ₹66.4 crore and a site of 8.2 acres.
When was it filed?
The application was filed on 9 Jan 2025.
Project details
| Official title | Proposed Construction of Residential Cum Commercial Project – "marina Bay" at Block/Survey No.: 1193 (Old Block/Survey No. 533/1), Moje: Umarsadi, Tal.: Pardi, Dist.: Valsad, Gujarat-396125 by Mr. Rutvik Jignesh Desai. |
|---|---|
| Status | Returned to applicant |
| Status since | 17 May 2025 |
| Application filed | 9 Jan 2025 |
| Approval sought | Coastal review |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Desai Rutvik |
| Land area | 8.2 acres (3.3 ha) |
| Project cost | ₹66.4 crore |
| Village / locality | Umarsadi |
| Taluk / tehsil | Pardi |
| District | Valsad |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-14922 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 9 Jan 2025 (this page) | Returned to applicant | 8.2 acres | ₹66.4 crore |
| New project filed 28 Nov 2024 | Withdrawn | 8.2 acres | ₹66.4 crore |
What the filings say
What is planned
Mr. Rutvik Jignesh Desai proposes the construction of "Marina Bay," a residential-cum-commercial project in Umarsadi, Valsad. The applicant's project report describes a development consisting of 108 flats, 129 bungalows, and 40 commercial shops, along with a society office and multipurpose hall.
The residential component is divided into several building types:
- Flats (A and B Types): Two blocks (A1+A2+A3 and B1+B2+B3) rising to a height of approximately 18.47 metres. These include ground-floor shops and five upper floors containing 104 units of 2 BHK flats and 4 units of 3 BHK flats.
- Bungalows (C to I Types): A total of 129 units ranging from 3 BHK to 6 BHK configurations. Most are ground-plus-one-floor structures (6.45 metres high), while some types (F, G, H, and I) include a second floor, reaching up to 9.46 metres.
- Commercial: 40 shops located on the ground floors of the flat blocks.
- Amenities: A dedicated society office building (J Type) with a multipurpose hall and waiting lounge.
| Item | Detail |
|---|---|
| Total Plot Area | 33,202.00 sq. m. |
| Total Built-up Area | 35,643.78 sq. m. |
| FSI Area | 30,031.07 sq. m. |
| Total Residential Units | 237 (108 Flats + 129 Bungalows) |
| Total Commercial Units | 40 Shops |
| Total Parking Area | 7,486.04 sq. m. |
| Estimated Project Cost | ₹66.6 crore |
Land and surroundings
The project site is located on 3.32 hectares (8.20 acres) of private non-agricultural land. It is situated adjacent to the Par River and the Coastal Highway. The applicant states that the site partly falls within Coastal Regulation Zone (CRZ) categories CRZ IA (50m mangrove buffer zone), CRZ IB, and CRZ II, with the remaining area outside the CRZ. The proposed buildings are planned completely inside the 'Port Limit'.
Surrounding landmarks include the Umarsadi Beach (1.24 km west) and the Arabian Sea (1.69 km west). No national parks or wildlife sanctuaries are located within a 10 km radius, though the Parnera Hill reserved forest is 5.6 km to the northeast.
Water, power and access
During the operational phase, the total water requirement is estimated at 239.0 KLD. Fresh water (109.0 KLD) will be sourced from the Umarsadi-Machhiwad Gram Panchayat, while the remaining 130.0 KLD will be met through recycled water. A Sewage Treatment Plant (STP) with a capacity of 170.0 KLD is proposed to treat domestic wastewater. Treated water will be reused for flushing, vehicle washing, and gardening.
Power will be supplied by Dakshin Gujarat Vij Company Limited (DGVCL), with a total operational requirement of 1,910 KWH. Two diesel generator sets of 500 KVA each are planned for backup. The project also includes 172 KW of rooftop solar installations covering 8,268.05 sq. m. of terrace space.
Environmental safeguards
The applicant proposes a greenbelt covering 10,958.0 sq. m. (approximately 33% of the plot area), which will include the planting of 2,291 trees. For solid waste management, an organic waste converter with a capacity of 400 kg/day will process biodegradable waste into manure for use on-site. Non-biodegradable waste will be collected and disposed of as per municipal rules. Rainwater harvesting will be managed through a collection system and nine recharge wells.
Timeline
The project implementation schedule estimates a total construction period of approximately 33 months from the start of work. Key phases include:
- Foundation and plinth work: 4 months
- Bungalow construction (Ground to 2nd floor): 12 months
- Flat construction (Ground to 5th floor): 8 months
- Finishing works (Plaster, plumbing, electrification, and painting): 14 months (overlapping)
Mr. Rutvik Jignesh Desai Residential Cum Commercial Project – "marina Bay" site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
64 applications in Valsad since January 2022 are in the same category (Buildings & townships): 46 approved, 10 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 8.2 acres, this one is larger than 73% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Umarsadi, Pardi, Valsad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Residential Cum Commercial Project – "marina Bay" at Block/Survey No.: 1193… — withdrawn, 0 m away
- Project by Atul Limited — initial checks, 4.2 km away
- Crz Clearance for New Proposed Pipeline for Disposal of Treated Wastewater… — coastal clearance granted, 4.2 km away
- Pardi underground Drainage Line Phase-II (UGD) project — more information requested, 5.5 km away
- Forest land proposal for Diversion for Social Forest Land proposal for forest… — forest land use approved, 6.2 km away
- Forest land proposal for Diversion for Social Forest Land proposal for forest… — lapsed, 6.2 km away
- 125 mm PE Gas pipeline connectivity from CNG Station Parnera to Potential… — forest land use approved, 6.5 km away
- 4" Steel Pipeline and 125/90mm Dia PE at Pariya Road, Velaparva Road to… — lapsed, 6.6 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.