Quick answers
What is Swarnim Greens?
Swarnim Greens is an approved mixed-use project in Adalaj (Ct), Gandhinagar, Gujarat. It plans 87 units in 1 tower of up to 20 floors on 1.1 acres.
Who is building it?
The applicant is Gopinath Developer.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 9 Aug 2024), as of 27 Nov 2026.
Where is it?
In Adalaj (Ct), Gandhinagar, Gujarat.
How big is it?
It has a stated cost of ₹59 crore and a site of 1.1 acres.
When was it filed?
The application was filed on 28 Mar 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 9 Aug 2024 |
| Application filed | 28 Mar 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Gopinath Developer |
| Use | Mixed use |
| Units | 87 |
| Towers | 1 |
| Floors (tallest) | 20 |
| Basements | 3 |
| Parking spaces | 271 |
| Land area | 1.1 acres (0.5 ha) |
| Built-up area | 36,786 m² (3,95,961 sq ft) |
| Plot area | 4,615 m² (49,675 sq ft) |
| Project cost | ₹59 crore |
| Village / locality | Adalaj (Ct) |
| Taluk / tehsil | Gandhinagar |
| District | Gandhinagar |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-03302 |
What the filings say
What is planned
Swarnim Greens is a mixed-use building project proposed by Gopinath Developer. The applicant's project report describes a development consisting of two blocks (A and B) with a total built-up area of 36,785.79 square metres on a plot of 0.46 hectares (1.14 acres). The project is designed for both residential and commercial use, featuring 70 residential units and 17 commercial units.
The building structure includes three basement levels for parking, a ground floor, and 20 upper floors. The ground floor is planned for shops and residential foyer space. The first floor is dedicated to commercial offices, while the second floor and above are primarily for residential use. The tallest building height is planned for 20 floors above ground.
| Item | Detail |
|---|---|
| Total Built-up Area | 36,785.79 square metres |
| Total FSI Area | 18,459.82 square metres |
| Residential Units | 70 |
| Commercial Units | 17 |
| Total Parking Area | 8,581.05 square metres |
| Total Project Cost | ₹59 crore |
| Power Requirement | 855 KW |
Layout and design
The site layout includes 8.5 to 9.0-metre wide internal approach roads, with primary entry from a 90.0-metre wide road. The design incorporates a common plot area of 557.76 square metres. For parking, the applicant has proposed a total of 271 Equivalent Car Spaces (ECS) across three basements and hollow plinth areas.
Architectural features include cantilever balconies to provide shading for large windows and roof insulation using bricks to protect the top floor from heat. The building is designed to maximize natural light and air circulation to reduce energy consumption. A fire safety plan has been approved, including a dedicated fire lift, hydrant systems with a 1,00,000-litre underground tank, and a 20,000-litre overhead tank.
Water, power and access
During the operational phase, the total water requirement is estimated at 65.3 kilolitres per day (KLD). This consists of 41.1 KLD of fresh water, to be supplied by the Gandhinagar Urban Development Authority (GUDA), and 24.2 KLD of recycled water. For the construction phase, approximately 9 KLD will be sourced via tankers.
Electricity will be provided by Uttar Gujarat Vij Company Limited (UGVCL) with a total demand of 855 KW. A 125 KVA diesel generator set is planned for power backup. The site is located near the Sarkhej-Gandhinagar Highway, approximately 2.57 km from Khodiyar Railway Station and 11.9 km from Ahmedabad Airport.
Environmental safeguards
The applicant proposes to install an on-site Sewage Treatment Plant (STP) to treat 52.1 KLD of sewage. Treated water will be reused for flushing and gardening, with the surplus discharged into the GUDA drainage line. Solid waste management includes the provision of 17 container bins (9 for residential and 8 for commercial use), with organic waste to be processed in an Organic Waste Convertor.
To manage stormwater and recharge groundwater, the plan includes two percolation wells. A greenbelt area of 789.76 square metres is proposed, with a plan to plant 116 trees along the periphery. For air quality management during construction, water sprinkling and the use of vehicles with valid pollution certificates are proposed. Noise-generating equipment will be fitted with silencers and restricted to daytime operation.
Swarnim Greens site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
472 applications in Gandhinagar since January 2022 are in the same category (Buildings & townships): 365 approved, 79 filed or under review, and 28 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 1.1 acres, this one is smaller than 70% of them.
147 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Adalaj (Ct), Gandhinagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Atishay Shivalay 4 — environmental approval granted, 150 m away
- The Venezia — under environmental review, 150 m away
- The Venezia — environmental approval granted, 150 m away
- Chandarana — environmental approval granted, 300 m away
- Chandarana — environmental approval granted, 300 m away
- The Opus — environmental approval granted, 500 m away
- Adani University Project — environmental approval granted, 1000 m away
- Pearl Ocean — environmental approval granted, 1.5 km away
More from Gopinath Developer in Gandhinagar
- The Address — environmental approval granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.