The Venezia is an approved residential project in Adalaj (Ct), Gandhinagar, Gujarat. It plans 146 units in 3 towers of up to 19 floors on 1.3 acres. Its stated project cost is ₹77.6 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 19 Sept 2025).

See it on the live map All projects in Gandhinagar

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is The Venezia?

The Venezia is an approved residential project in Adalaj (Ct), Gandhinagar, Gujarat. It plans 146 units in 3 towers of up to 19 floors on 1.3 acres.

Who is building it?

The applicant is R M Enterprise.

Has it been approved?

Yes. Its status is “Environmental approval granted” (since 19 Sept 2025), as of 27 Nov 2026.

Where is it?

In Adalaj (Ct), Gandhinagar, Gujarat.

How big is it?

It has a stated cost of ₹77.6 crore and a site of 1.3 acres.

When was it filed?

The application was filed on 13 Apr 2025.

Project details

StatusEnvironmental approval granted
Status since19 Sept 2025
Application filed13 Apr 2025
Approval soughtEnvironmental approval
Application typeNew project
SectorBuildings & townships
ApplicantR M Enterprise
UseResidential
Units146
Towers3
Floors (tallest)19
Basements2
Parking spaces297
Land area1.3 acres (0.5 ha)
Built-up area38,534 m² (4,14,776 sq ft)
Plot area5,392 m² (58,039 sq ft)
Project cost₹77.6 crore
Village / localityAdalaj (Ct)
Taluk / tehsilGandhinagar
DistrictGandhinagar
StateGujarat
Location fromSite boundary on record
Our referenceWID-GJ-09041

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Expansion filed 8 Apr 2026Under environmental review1.3 acres₹77.6 crore
New project filed 13 Apr 2025 (this page)Environmental approval granted1.3 acres₹77.6 crore

What the filings say

What is planned

The applicant, R M Enterprise, proposes a residential development consisting of three high-rise blocks. According to the project layout and environmental clearance documents, Blocks A and B are designed with two basements, a ground floor (hollow plinth), and 19 upper floors. Block C is planned with two basements, a ground floor, and 18 upper floors. The project will provide a total of 146 residential units.

Layout and design

The total built-up area for the project is 38,533.55 square metres, with a Floor Space Index (FSI) area of 21,561.95 square metres. The site includes a common plot of 616.48 square metres. Parking is distributed across the two basement levels and the hollow plinth, providing a total of 297 car parking spaces. The building design incorporates four lifts for Block A and two lifts each for Blocks B and C, including dedicated fire lifts.

ItemDetail
Total Residential Units146
Number of Blocks3
Tallest Building HeightG+19 floors
Total Built-up Area38,533.55 sq. m.
STP Capacity150 KLD
Car Parking Spaces297
Green Belt Area616.48 sq. m.
CER Allocation₹1.56 crore

Water, power and access

During the operation phase, the total water requirement is estimated at 164.03 kilolitres per day (KLD). The applicant's report states that 113.27 KLD will be fresh water sourced from the local authority, while 50.76 KLD will be recycled treated water used for flushing and gardening. A Sewage Treatment Plant (STP) with a capacity of 150 KLD is proposed to treat 125.04 KLD of generated sewage.

For back-up power, the applicant plans to install one 125 KVA diesel generator set equipped with an acoustic enclosure. Access to the site is provided via an 18-metre wide Town Planning Scheme (TPS) road.

Environmental safeguards

The applicant has allocated 616.48 square metres (0.15 acres) for a green belt, representing approximately 10% of the total plot area. This space will include the plantation of 135 trees. For storm water management, two percolation wells are planned to recharge ground water. Solid waste will be segregated at the source, with biodegradable waste treated in an on-site Organic Waste Converter (OWC).

Fire safety provisions include an underground fire water tank of 2,00,000 litres and an overhead tank of 60,000 litres. The buildings will be equipped with wet risers, automatic sprinklers in the basement and high-rise areas, and manually operated electric fire alarm systems.

Corporate Environmental Responsibility (CER)

The environmental clearance letter specifies a CER fund of ₹1.56 crore (₹156 lakh). Planned activities include the beautification of the Dantaliya village pond, which involves deepening the pond and planting 750 trees. Other initiatives include installing solar street lights and providing infrastructure such as rooftop solar and percolation wells at the Ambapur village primary school and the Tarapur government primary health centre.

Timeline

A geotechnical investigation was conducted in late 2024, involving nine boreholes drilled to a depth of 45 metres. Environmental approval for the initial proposal was granted on 19 September 2025. A subsequent application for expansion was filed in April 2026 and is currently under environmental review.

The Venezia site plan and layout

4 drawings from the project's filings. Sign in free to see them.

The Venezia: Location map: project site near Sarkhej-Gandhinagar Highway and Narmada Canal (preview)🔒 Sign in free to see it
Location map: project site near Sarkhej-Gandhinagar Highway and Narmada Canal
The Venezia: Satellite view of the project site and surrounding developments in Adalaj (preview)🔒 Sign in free to see it
Satellite view of the project site and surrounding developments in Adalaj
The Venezia: Layout plan: three residential blocks, common plot, and internal access roads (preview)🔒 Sign in free to see it
Layout plan: three residential blocks, common plot, and internal access roads
The Venezia: Rainwater harvesting scheme: detail of harvesting pit and desilting chamber (preview)🔒 Sign in free to see it
Rainwater harvesting scheme: detail of harvesting pit and desilting chamber

In context

472 applications in Gandhinagar since January 2022 are in the same category (Buildings & townships): 365 approved, 79 filed or under review, and 28 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 1.3 acres, this one is smaller than 54% of them.

140 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Adalaj (Ct), Gandhinagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.