Quick answers
What is this project?
Request for Transfer of Environmental Clearance (EC) from M/s. Essar Power Limited to M/s. ArcelorMittal Nippon Steel India Ltd. (Power Division – 500 MW CCPP) is an approved power project in Hajira, Chorasi, Surat, Gujarat. The site covers 64.9 acres.
Who is building it?
The applicant is Arcelormittal Nippon Steel India Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 7 Dec 2024), as of 27 Nov 2026.
Where is it?
In Hajira, Chorasi, Surat, Gujarat.
How big is it?
It has a stated cost of ₹1,131.8 crore and a site of 64.9 acres.
When was it filed?
The application was filed on 9 Nov 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 7 Dec 2024 |
| Application filed | 9 Nov 2024 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Power |
| Applicant | Arcelormittal Nippon Steel India Limited |
| Land area | 64.9 acres (26.3 ha) |
| Project cost | ₹1,131.8 crore |
| Village / locality | Hajira |
| Taluk / tehsil | Chorasi |
| District | Surat |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-03399 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Ownership transfer filed 9 Nov 2024 (this page) | Environmental approval granted | 64.9 acres | ₹1,131.8 crore |
| Ownership transfer filed 25 Jul 2024 | Withdrawn | 64.9 acres | ₹1,131.8 crore |
In context
39 applications in Surat since January 2022 are in the same category (Power): 22 approved, 13 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 9 months from filing to approval. At 64.9 acres, this one is larger than 85% of them.
42 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Hajira, Chorasi, Surat, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Request for Transfer of Environmental Clearance (EC) from M/s. Essar Power… — withdrawn, 0 m away
- Environmental Clearance (EC) name transfer from M/s. ArcelorMittal Nippon… — environmental approval granted, 1.2 km away
- Amalgamation of EC of "AMNSI 500 MW" with the EC of "Expansion of Integrated… — environmental approval granted, 1.2 km away
- Expansion of Integrated Steel Plant from 15.6 to 28.4 MTPA Liquid Steel of… — more information requested, 1.2 km away
- Application for M/S. Arcelormittal Nippon Steel India Limited to Include Long… — initial checks, 1.2 km away
- Proposed Expansion of Captive Power Plant Capacity from 270 MW to 300 MW — environmental approval granted, 2 km away
- Proposed Expansion of Captive Power Plant Capacity from 270 MW to 300 MW — environmental approval granted, 2 km away
- Proposed Expansion of Captive Power Plant Capacity from 270 MW to 300 MW — environmental approval granted, 2 km away
More from Arcelormittal Nippon Steel India Limited in Surat
- Environmental Clearance (EC) name transfer from M/s. ArcelorMittal Nippon… — environmental approval granted
- CRZ Clearance for "Laying of 16" 2.57 km dedicated Natural gas (NG) pipe line… — coastal clearance granted
- Amalgamation of EC of "AMNSI 500 MW" with the EC of "Expansion of Integrated… — environmental approval granted
- Application for M/S. Arcelormittal Nippon Steel India Limited to Include Long… — initial checks
9 Arcelormittal Nippon Steel projects in Surat
All 65 Arcelormittal Nippon Steel projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.