What is Silent Tower?
Silent Tower is an approved residential project in Abrama, Kamrej, Surat, Gujarat. It plans 434 units in 8 towers of up to 14 floors on 2.7 acres.
Who is building it?
The applicant is Dev Infra.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 7 Apr 2025), as of 27 Nov 2026.
Where is it?
In Abrama, Kamrej, Surat, Gujarat.
How big is it?
It has a stated cost of ₹85 crore and a site of 2.7 acres.
When was it filed?
The application was filed on 25 Nov 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 7 Apr 2025 |
| Application filed | 25 Nov 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Dev Infra |
| Use | Residential |
| Units | 434 |
| Towers | 8 |
| Floors (tallest) | 14 |
| Basements | 2 |
| Height | 45 m |
| Parking spaces | 617 |
| Land area | 2.7 acres (1.1 ha) |
| Built-up area | 72,254 m² (7,77,735 sq ft) |
| Plot area | 10,774 m² (1,15,970 sq ft) |
| Project cost | ₹85 crore |
| Village / locality | Abrama |
| Taluk / tehsil | Kamrej |
| District | Surat |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-06516 |
What the filings say
What is planned
The applicant, DEV INFRA, proposes to develop a residential project consisting of eight blocks, designated as Blocks A through H. According to the conceptual plan, each of the eight buildings will rise to a height of 14 floors above a ground level and two basement levels. The project is designed to provide a total of 434 dwelling units.
The residential units are distributed across the blocks with specific unit counts for each. Blocks A, B, D, F, and G are planned with 56 units each, while Block C will contain 60 units. Block E is designed for 42 units, and Block H will contain 64 units. The total built-up area for the development is stated as 72,253.79 square metres.
| Item | Detail |
|---|---|
| Total Blocks | 8 |
| Total Dwelling Units | 434 |
| Total Built-up Area | 72,253.79 sq.mt. |
| Max Building Height | 44.81 metres |
| Basement Levels | 2 |
| STP Capacity | 350 KLD |
| Solar Power Capacity | 200 KW |
| Proposed Tree Count | 270 |
| Green Area | 1,352.31 sq.mt. |
Layout and design
The site layout includes a network of internal roads to facilitate movement within the complex. These roads are planned to be 6.00 metres wide, with a central internal road reaching 7.50 metres in width. The ground floor is primarily dedicated to parking and entrance foyers for each block.
Two levels of basements are planned for parking and services. The first and second basements each cover an area of 8,290.01 square metres. The design incorporates specific ramp systems (Ramps A through D) with a 1:7 ratio to connect the basement levels with the ground floor.
Land and surroundings
The project is located in Abrama, within the Kamrej taluk of Surat. According to the key plan, the site is bordered by several adjacent plots, including Final Plot (FP) numbers 245, 238, 193, 267/a, and 243. The development is situated within the Preliminary Town Planning Scheme (TPS) No. 84.
Water, power and access
The project's water requirements will be supported by three underground storage tanks, each with a capacity of 2,46,000 litres. For wastewater management, the applicant proposes an MBAR-type Sewage Treatment Plant (STP) with a capacity of 350 kilolitres per day (KLD). Treated sewage is intended to be discharged into the Surat Municipal Corporation (SMC) drainage system.
Power will be supplemented by a 200 KW rooftop solar energy system, requiring approximately 1,200 square metres of terrace space. Diesel Generator (DG) sets are planned for emergency backup and will be housed in acoustic enclosures in the basement to minimize noise.
Environmental safeguards
The environmental management plan includes a green belt covering 1,352.31 square metres, which represents 12.55% of the total plot area. This area will consist of 900 square metres of lawn and 452.31 square metres of tree cover. The applicant plans to plant 270 trees of species such as Neem, Palm, Gulamhor, Asopalav, and Badam.
For solid waste management, an automatic Organic Waste Converter (OWC) with a capacity of 850 kg per day is proposed. Rainwater harvesting will be managed through a collection system and three recharge wells.
Timeline
The applicant's project report states that the entire project is expected to be completed within approximately four years. Environmental approval for the project was granted on 7 April 2025.
Silent Tower site plan and layout
4 drawings from the project's filings. Sign in free to see them.
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see it
🔒 Sign in free to see itIn context
489 applications in Surat since January 2022 are in the same category (Buildings & townships): 376 approved, 79 filed or under review, and 34 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 2.7 acres, this one is larger than 78% of them.
162 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Abrama, Kamrej, Surat, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Pratishtha Classic — environmental approval granted, 50 m away
- Lotus Valley — environmental approval granted, 150 m away
- Blue Stone One — environmental approval granted, 150 m away
- Blue Stone One — environmental approval granted, 150 m away
- Pratishtha Trade Center — environmental approval granted, 250 m away
- Green Sky — environmental approval granted, 250 m away
- Prime Living — environmental approval granted, 250 m away
- Prism Heights & Prism Business Center — environmental approval granted, 250 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.