Quick answers
What is this project?
Proposed expansion of M.S. Ingots/Billets, M.S. Rolling Products (CTD Bars, Angles Channel etc.) with addition of new products - Sponge Iron, WHRB based Power Plant and Coal based Power Plant by Sai Bandhan Infinium Pvt. Ltd is a lapsed industrial project in Chamardi, Vallabhipur, Bhavnagar, Gujarat. The site covers 36 acres.
Who is building it?
The applicant is Sai Bandhan Infinium Private Limited.
Has it been approved?
No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.
Where is it?
In Chamardi, Vallabhipur, Bhavnagar, Gujarat.
How big is it?
It has a stated cost of ₹210 crore and a site of 36 acres.
When was it filed?
The application was filed on 21 Jun 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 29 Oct 2024 |
| Application filed | 21 Jun 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Sai Bandhan Infinium Private Limited |
| Land area | 36 acres (14.6 ha) |
| Project cost | ₹210 crore |
| Village / locality | Chamardi |
| Taluk / tehsil | Vallabhipur |
| District | Bhavnagar |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-06837 |
In context
34 applications in Bhavnagar since January 2022 are in the same category (Industry): 18 approved, 11 filed or under review, and 5 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 36 acres, this one is larger than 82% of them.
6 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Chamardi, Vallabhipur, Bhavnagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed expansion of metallurgical unit by M/s. Sai Infinium Limited — lapsed, 0 m away
- Industrial project by Sai Bandhan Infinium Pvt. Ltd. — environmental approval granted, 200 m away
- Proposed expansion of metallurgical unit by M/s. Sai Infinium Limited — under environmental review, 250 m away
- Proposed Project for Manufacturing of Various Synthetic Organic Chemicals by… — lapsed, 4.8 km away
- Proposed Project for Manufacturing of Various Synthetic Organic Chemicals by… — environmental approval granted, 4.8 km away
- Proposed Project for Manufacturing of Various Synthetic Organic Chemicals by… — withdrawn, 4.8 km away
- Construction & Improvement of Ghanghali Bhangadh Paliyad road — lapsed, 5.8 km away
- 66 KV S/C line from Exist. Ghanghali-3 SS to Prop. M/s. M.G. Steel SS with 66… — forest land use approved, 6.7 km away
More from Sai Bandhan Infinium Private Limited in Bhavnagar
- Proposed expansion of metallurgical unit by M/s. Sai Infinium Limited — under environmental review
- Proposed expansion of metallurgical unit by M/s. Sai Infinium Limited — lapsed
All 4 Sai Bandhan Infinium projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.