Quick answers
What is Skyclad?
Skyclad is a proposed building project in Sargasan, Gandhinagar, Gujarat. The site covers 1.3 acres.
Who is building it?
The applicant is Status Sharan Infra.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Sargasan, Gandhinagar, Gujarat.
How big is it?
It has a stated cost of ₹44.5 crore and a site of 1.3 acres.
When was it filed?
The application was filed on 8 Aug 2026.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Skyclad
Project details
| Status | Initial checks |
|---|---|
| Status since | 3 Oct 2026 |
| Application filed | 8 Aug 2026 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Buildings & townships |
| Applicant | Status Sharan Infra |
| Land area | 1.3 acres (0.5 ha) |
| Project cost | ₹44.5 crore |
| Village / locality | Sargasan |
| Taluk / tehsil | Gandhinagar |
| District | Gandhinagar |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-09596 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 8 Aug 2026 (this page) | Initial checks | 1.3 acres | ₹44.5 crore |
| New project filed 6 Jul 2024 | Environmental approval granted | 1.3 acres | ₹43.5 crore |
What the filings say
What is planned
Status Sharan Infra is developing a mixed-use commercial and residential project named Skyclad in Sargasan, Gandhinagar. According to the environmental approval granted in January 2025, the project involves the construction of a single building block with two basements, a ground floor or hollow plinth, and 13 upper floors. The maximum height of the building is specified as 44.97 metres.
The project is designed to accommodate 192 total units, comprising 156 residential apartments and 36 commercial units (shops). The residential component is distributed across three blocks (A, B, and C) from the first to the thirteenth floors. The commercial units are located on the ground floor.
| Item | Detail |
|---|---|
| Total Units | 192 (156 Residential, 36 Commercial) |
| Building Configuration | 2 Basements + GF/Hollow Plinth + 13 Floors |
| Maximum Building Height | 44.97 metres |
| Total Parking Space | 6,508 square metres (208 CPS) |
| Fresh Water Requirement | 51.5 KLD (Operation) |
| Sewage Treatment Plant Capacity | 65.4 KLD |
| Green Belt Area | 766.08 square metres |
| Solar Power Generation | 68.68 KW |
Layout and design
The building layout includes three residential blocks (A, B, and C) served by multiple lifts. Blocks A and C are each equipped with two lifts (one passenger and one fire lift), while Block B also features two lifts. The internal floor plans for residential units include typical 3BHK configurations with drawing, living, and dining areas, three bedrooms, kitchen, store, and multiple toilets.
Parking is distributed across several levels. The first basement provides 2,790.94 square metres, the second basement provides 3,154.93 square metres, the hollow plinth offers 244.92 square metres, and 317.21 square metres is allocated for open surface parking. The applicant has proposed a basement height greater than 4.5 metres to allow for future mechanical parking systems. The peripheral margin for the project is set at 6 metres, with internal roads also 6 metres wide.
Water, power and access
During the operation phase, the total water requirement is estimated at 80.7 kilolitres per day (KLD). Of this, 51.5 KLD of fresh water will be supplied by the Gandhinagar Municipal Corporation (GMC), while the remaining 29.2 KLD will be met through treated sewage. A dual plumbing system will be installed to use treated water for flushing and gardening. For construction, 2.25 KLD of water will be sourced via tankers.
Power will be sourced from the local grid, with a 125 KVA diesel generator (DG) set proposed for backup. Energy conservation measures include the installation of a 68.68 KW solar power system, LED lighting for common areas, and the use of aerated blocks for thermal insulation. Access to the site is provided via separate entries and exits on the approach road.
Environmental safeguards
The applicant plans to install an onsite Sewage Treatment Plant (STP) with a capacity of 65.4 KLD. Biodegradable waste will be processed in an onsite Organic Waste Converter, while recyclable materials will be sold to vendors. For stormwater management, two percolation wells are planned for groundwater recharging.
A green belt of 766.08 square metres will be developed, including a 256-square-metre tree-covered area where 128 indigenous trees will be planted. Fire safety provisions include fire extinguishers on each floor, smoke detectors, sprinklers, a 150 KL underground water tank, and a 20 KL terrace water tank.
Corporate Environmental Responsibility
The project proponent has committed ₹87 lakh for Corporate Environmental Responsibility (CER) activities. These include tree plantation with guards and maintenance along the adjacent Town Planning (TP) road, installation of solar street lights on the same road, and providing solar panels to a local urban health centre. These activities are scheduled for completion within three years of the project's commencement.
Skyclad site plan and layout
A drawing from the project's filings. Sign in free to see it.
🔒 Sign in free to see itIn context
472 applications in Gandhinagar since January 2022 are in the same category (Buildings & townships): 365 approved, 79 filed or under review, and 28 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 1.3 acres, this one is smaller than 60% of them.
165 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Sargasan, Gandhinagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Skyclad — environmental approval granted, 0 m away
- Saffron flora — environmental approval granted, 300 m away
- The Offices by Hari Group — environmental approval granted, 450 m away
- The Offices by Hari Group — environmental approval granted, 450 m away
- Sahajanand Shikhar — environmental approval granted, 450 m away
- Sahstra Swaraj — lapsed, 500 m away
- Shailya Nivasa — environmental approval granted, 550 m away
- Keshav Parisar — environmental approval granted, 600 m away
About this information