What is Captive Power Plant (2x30 MW)?
Captive Power Plant (2x30 MW) is a proposed power project in Thumdi, Abdasa, Kachchh, Gujarat. The site covers 34.8 acres.
Who is building it?
The applicant is Vadraj Energy (Gujarat) Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Thumdi, Abdasa, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹456 crore and a site of 34.8 acres.
When was it filed?
The application was filed on 30 Sept 2026.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 16 Nov 2026 |
| Application filed | 30 Sept 2026 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Power |
| Applicant | Vadraj Energy (Gujarat) Limited |
| Land area | 34.8 acres (14.1 ha) |
| Project cost | ₹456 crore |
| Village / locality | Thumdi |
| Taluk / tehsil | Abdasa |
| District | Kachchh |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-10869 |
In context
75 applications in Kachchh since January 2022 are in the same category (Power): 30 approved, 30 filed or under review, and 11 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 34.8 acres, this one is larger than 58% of them.
6 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Thumdi, Abdasa, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Setting up of Cement Plant (3.3 MMTA) — environmental approval granted, 250 m away
- Setting up of Cement Plant (3.3 MMTA) — environmental approval granted, 250 m away
- Setting up of Cement Plant (3.3 MMTA) — returned to applicant, 250 m away
- Permission for Diversion of 0.1001 Ha Forest land of Karmata Village, Ta:… — more information requested, 2.6 km away
- Diversion of Forest land of Village: Laiyari( Ta: Abdasa) and Village: Maniara… — more information requested, 4.2 km away
- Name change in Environmental Clearance of Naniber Limestone Mining Project of… — lapsed, 4.4 km away
- Jetty and Desalination Plant — environmental approval granted, 6.1 km away
- Transfer of Environmental Clearance and its amendment granted to Sanghi… — environmental approval granted, 6.9 km away
About this information