Diversion of Forest land of Village: Laiyari( Ta: Abdasa) and Village: Maniara (Ta: dayapar) Village for laying of underground water pipeline in favour of Gujarat Water Supply and Sewerage Board in Dist: Kutch of Gujarat State is a proposed pipeline project in Maniara, Lakhpat, Kachchh, Gujarat. It seeks 1 acre of forest land.
Who is building it?
The applicant is Gujarat Water Supply & Sewerage Board, P.H..S Sub Dn. No.1 Naliya.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Maniara, Lakhpat, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹45 crore and 1 acres (0.4 ha) of forest land.
When was it filed?
The application was filed on 8 Jun 2026.
Project details
| Status | More information requested |
|---|---|
| Status since | 3 Nov 2026 |
| Application filed | 8 Jun 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Pipelines |
| Applicant | Gujarat Water Supply & Sewerage Board, P.H..S Sub Dn. No.1 Naliya |
| Forest land | 1 acres (0.4 ha) |
| Project cost | ₹45 crore |
| Village / locality | Maniara |
| Taluk / tehsil | Lakhpat |
| District | Kachchh |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-12556 |
In context
59 applications in Kachchh since January 2022 are in the same category (Pipelines): 21 approved, 25 filed or under review, and 13 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval.
6 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Maniara, Lakhpat, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Name change in Environmental Clearance of Naniber Limestone Mining Project of… — lapsed, 4.1 km away
- Captive Power Plant (2x30 MW) — under environmental review, 4.2 km away
- Setting up of Cement Plant (3.3 MMTA) — environmental approval granted, 4.2 km away
- Setting up of Cement Plant (3.3 MMTA) — environmental approval granted, 4.2 km away
- Setting up of Cement Plant (3.3 MMTA) — returned to applicant, 4.2 km away
- Permission for Diversion of 0.1001 Ha Forest land of Karmata Village, Ta:… — more information requested, 4.3 km away
- Diversion of 0.8330 Ha proposed Roadside Protected Forest land of Naredo to… — lapsed, 7.8 km away
- Motiber Silica Sand Mine (ML Area: 160.7582 Ha) with expansion in production… — more information requested, 8.1 km away
More from Gujarat Water Supply & Sewerage Board, P.H..S Sub Dn. No.1 Naliya in Kachchh
- Diversion of 0.3490 Ha Forest Land of Naliya Narayansarovar Road for Laying of… — more information requested
- Diversion of 0.4627 Ha Forest land of Naliya Narayansarovar Road for laying of… — more information requested
- Diversion of Forest land for the laying of Proposed Underground Water Pipeline… — forest land use approved
- Diversion of Forest Land for Laying of Underground Water Pipeline and… — forest land use approved
- Laying of Underground Water Pipeline to Roadside Forest of Bhuj Khavada Road — more information requested
- Laying of Underground Drinking Water Pipeline Through the Roadside Protected… — more information requested
All 28 Gujarat Water Supply & Sewerage Board, P.H..S Sub Dn. No.1 Naliya projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.