Forest land use approvedPower · Kachchh, Gujarat

2 Nos. of 765 KV D/C Power Transmission lines between M/s. Reliance Industries Limited, Pooling Substation at Z2 Land Parcel, District Kachchh upto M/s Reliance Industries Limited Receiving Substation at Jamnagar Manufacturing Division (JMD), District Jamnagar for the purpose of evacuation of 9000 MW Solar Power in the State of Gujarat

2 Nos. of 765 KV D/C Power Transmission lines between M/s. Reliance Industries Limited, Pooling Substation at Z2 Land Parcel, District Kachchh upto M/s Reliance Industries Limited Receiving Substation at Jamnagar Manufacturing Division (JMD), District Jamnagar for the purpose of evacuation of 9000 MW Solar Power in the State of Gujarat is an approved power project in Shikharpur, Bhachau, Kachchh, Gujarat. The site covers 17,341.3 acres. Its stated project cost is ₹2,500 crore. As of 27 Nov 2026, its status is “Forest land use approved” (since 4 Nov 2026).

See it on the live map All projects in Kachchh

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

2 Nos. of 765 KV D/C Power Transmission lines between M/s. Reliance Industries Limited, Pooling Substation at Z2 Land Parcel, District Kachchh upto M/s Reliance Industries Limited Receiving Substation at Jamnagar Manufacturing Division (JMD), District Jamnagar for the purpose of evacuation of 9000 MW Solar Power in the State of Gujarat is an approved power project in Shikharpur, Bhachau, Kachchh, Gujarat. The site covers 17,341.3 acres.

Who is building it?

The applicant is Reliance Industries Limited.

Has it been approved?

Yes. Its status is “Forest land use approved” (since 4 Nov 2026), as of 27 Nov 2026.

Where is it?

In Shikharpur, Bhachau, Kachchh, Gujarat.

How big is it?

It has a stated cost of ₹2,500 crore; a site of 17,341.3 acres and 189.5 acres (76.7 ha) of forest land.

When was it filed?

The application was filed on 11 Apr 2025.

Project details

Official titleProposed Installation of 2 Nos. of 765 KV D/C Power Transmission lines between M/s. Reliance Industries Limited, Pooling Substation at Z2 Land Parcel, District Kachchh upto M/s Reliance Industries Limited Receiving Substation at Jamnagar Manufacturing Division (JMD), District Jamnagar for the purpose of evacuation of 9000 MW Solar Power in the State of Gujarat.
StatusForest land use approved
Status since4 Nov 2026
Application filed11 Apr 2025
Approval soughtForest land use
Application typeNew project
SectorPower
ApplicantReliance Industries Limited
Land area17,341.3 acres (7,017.8 ha)
Forest land189.5 acres (76.7 ha)
Project cost₹2,500 crore
Village / localityShikharpur
Taluk / tehsilBhachau
DistrictKachchh
StateGujarat
Location fromSite boundary on record
Our referenceWID-GJ-12131

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 11 Apr 2025 (this page)Forest land use approved17,341.3 acres₹2,500 crore
New project filed 9 Apr 2025Coastal clearance granted17,341.3 acres₹2,500 crore

In context

75 applications in Kachchh since January 2022 are in the same category (Power): 30 approved, 30 filed or under review, and 11 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 17,341.3 acres, this one is larger than 91% of them.

Where it is

Shikharpur, Bhachau, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Reliance Industries Limited in Kachchh

9 Reliance Industries projects in Kachchh
All 60 Reliance Industries projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.