What is this project?
Diversion of Protected Forest Land for Entry and Exit Approach to Proposed Hindustan Petroleum Corporation Limited (HPCL) Retail Outlet is a lapsed road project in Lakhtar, Surendranagar, Gujarat. The site covers 0.1 acres.
Who is building it?
The applicant is Vasava Sureshbhai M.
Has it been approved?
No. The application was lapsed on 19 Sept 2026, so it is no longer under consideration.
Where is it?
In Lakhtar, Surendranagar, Gujarat.
How big is it?
It has a stated cost of ₹50 lakh; a site of 0.1 acres and 410 m² of forest land.
When was it filed?
The application was filed on 14 Jul 2026.
Project details
| Official title | Diversion of Protected Forest Land for Entry and Exit Approach to Proposed Hindustan Petroleum Corporation Limited (HPCL) Retail Outlet at Village Lakhtar, District Surendranagar, Gujarat |
|---|---|
| Status | Lapsed |
| Status since | 19 Sept 2026 |
| Application filed | 14 Jul 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Vasava Sureshbhai M |
| Land area | 400 m² |
| Forest land | 410 m² |
| Project cost | ₹50 lakh |
| Village / locality | Lakhtar |
| Taluk / tehsil | Lakhtar |
| District | Surendranagar |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-12275 |
In context
12 applications in Surendranagar since January 2022 are in the same category (Roads & highways): 1 approved, 7 filed or under review, and 4 withdrawn, lapsed or rejected. At 0.1 acres, this one is smaller than 91% of them.
Where it is
Lakhtar, Surendranagar, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Industrial project by M/s. MARUTINANDAN ENGINEERING CREATIONS PRIVATE LIMITED — returned to applicant, 5.3 km away
- Industrial project by M/s. Marutinandan Engineering Creations Pvt. Ltd. — environmental approval granted, 5.5 km away
- Industrial project by M/s. Marutinandan Engineering Creations Pvt. Ltd. — cleared for impact study, 5.5 km away
- Permission for laying of Optical Fiber Cable from (1) Surendranagar – Dudhrej… — more information requested, 10.9 km away
- 765 kV D/c Halvad-Vataman Transmission Line (PVTL) — forest land use approved, 15.6 km away
- Proposed Secured Landfill Facility (Capacity - 56,60,000 m3) of M/s. Greeneco… — cleared for impact study, 17.8 km away
- Two Lane of Existing Rajsitapur to Sarval Road — more information requested, 18 km away
- Proposed Expansion of Synthetic Organic Chemicals (Reactive Dyes)manufacturing… — environmental approval granted, 18.8 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.