Quick answers
What is this project?
765 kV D/C KPS3 (GIS) – Lakadia (AIS) Transmission Line for "Evacuation of power from potential renewable energy zone in Khavda area of Gujarat under Khavda Phase-IV (7GW): Part A." is an approved power project in Vijpasar, Bhachau, Kachchh, Gujarat. It seeks 784.8 acres of forest land.
Who is building it?
The applicant is Sunrays Infra Space Two Limited.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 4 Jul 2026), as of 27 Nov 2026.
Where is it?
In Vijpasar, Bhachau, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹631.2 crore and 784.8 acres (317.6 ha) of forest land.
When was it filed?
The application was filed on 2 Feb 2024.
Project details
| Official title | Construction of 765 kV D/C KPS3 (GIS) – Lakadia (AIS) Transmission Line for "Evacuation of power from potential renewable energy zone in Khavda area of Gujarat under Khavda Phase-IV (7GW): Part A." |
|---|---|
| Status | Forest land use approved |
| Status since | 4 Jul 2026 |
| Application filed | 2 Feb 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | Sunrays Infra Space Two Limited |
| Forest land | 784.8 acres (317.6 ha) |
| Project cost | ₹631.2 crore |
| Village / locality | Vijpasar |
| Taluk / tehsil | Bhachau |
| District | Kachchh |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-12673 |
In context
75 applications in Kachchh since January 2022 are in the same category (Power): 30 approved, 30 filed or under review, and 11 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval.
Where it is
Vijpasar, Bhachau, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Power project by Khavda II-A Transmission Limited — decision issued, 9.7 km away
- Power project by Khavda II-A Transmission Limited — forest land use approved, 9.7 km away
- Proposed "765 kV D/C from Khavda-II PS (GIS) to Lakadia (PS) Transmission… — lapsed, 14.5 km away
- Shri Balvantsinh K. Jadeja — environmental approval granted, 18.1 km away
- Jam Hambhuji Pruthavirajji — environmental approval granted, 18.3 km away
- Diversion of 0.7639 Ha. Forest land for Development Tourism based… — lapsed, 18.8 km away
- Diversion of 0.8104 Ha. of Kutch Desert Sanctuary land for Development Tourism… — under wildlife review, 19 km away
- Gadhvi Zeel Hareshbhai (Jam Kunariya Ordinary Sand Block - C) — lapsed, 19 km away
More from Sunrays Infra Space Two Limited in Kachchh
- 765 kV D/C KPS3 (GIS) – Lakadia (AIS) Transmission Line for "Evacuation of… — under wildlife review
- 765 kV D/C KPS1 (GIS) – Bhuj PS 2nd Transmission Line for "Evacuation of power… — forest land use approved
All 3 Sunrays Infra Space Two projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.