What is this project?
765 kV D/C KPS3 (GIS) – Lakadia (AIS) Transmission Line for "Evacuation of power from potential renewable energy zone in Khavda area of Gujarat under Khavda Phase-IV (7GW): Part A." is a proposed power project in Adhoi (Pasakayara), Bhachau, Kachchh, Gujarat. The site covers 1,569.6 acres.
Who is building it?
The applicant is Sunrays Infra Space Two Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under wildlife review”, as of 27 Nov 2026.
Where is it?
In Adhoi (Pasakayara), Bhachau, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹631.2 crore and a site of 1,569.6 acres.
When was it filed?
The application was filed on 3 Feb 2024.
Project details
| Official title | Construction of 765 kV D/C KPS3 (GIS) – Lakadia (AIS) Transmission Line for "Evacuation of power from potential renewable energy zone in Khavda area of Gujarat under Khavda Phase-IV (7GW): Part A." |
|---|---|
| Status | Under wildlife review |
| Status since | 6 Nov 2026 |
| Application filed | 3 Feb 2024 |
| Approval sought | Wildlife review |
| Application type | New project |
| Sector | Power |
| Applicant | Sunrays Infra Space Two Limited |
| Land area | 1,569.6 acres (635.2 ha) |
| Project cost | ₹631.2 crore |
| Village / locality | Adhoi (Pasakayara) |
| Taluk / tehsil | Bhachau |
| District | Kachchh |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-14576 |
In context
75 applications in Kachchh since January 2022 are in the same category (Power): 30 approved, 30 filed or under review, and 11 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 1,569.6 acres, this one is larger than 90% of them.
Where it is
Adhoi (Pasakayara), Bhachau, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 4G Saturation USOF Kachchh CAT-5/6 — under forest review, 9.1 km away
- 4G Saturation USOF Kachchh CAT-5/6 — application filed, 9.1 km away
- Permission for Underground Ofc Laying Work — lapsed, 14.5 km away
- Diversion of 3.55 Ha Forest Land for the Laying of Proposed Underground… — more information requested, 15.3 km away
- Shri Notiyar Abdreman Anvar — lapsed, 16 km away
- Permission for Underground Ofc Laying Work — lapsed, 16 km away
- Gagal Damji Naran — initial checks, 16.2 km away
- Sumrasar to Bhirandiyara BSNL OFC Route — forest land use approved, 16.2 km away
More from Sunrays Infra Space Two Limited in Kachchh
- 765 kV D/C KPS3 (GIS) – Lakadia (AIS) Transmission Line for "Evacuation of… — forest land use approved
- 765 kV D/C KPS1 (GIS) – Bhuj PS 2nd Transmission Line for "Evacuation of power… — forest land use approved
All 3 Sunrays Infra Space Two projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.