Epc Work for Construction of Pipeline Project From Tappar Dam to Nirona Dam(Northern Link) is a proposed pipeline project in Bhuj (M), Bhuj, Kachchh, Gujarat. The site covers 143.7 acres.
Who is building it?
The applicant is Department of Irrigation.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Bhuj (M), Bhuj, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹1,350 crore; a site of 143.7 acres and 53.3 acres (21.6 ha) of forest land.
When was it filed?
The application was filed on 28 Jul 2023.
Project details
| Status | More information requested |
|---|---|
| Status since | 16 Apr 2026 |
| Application filed | 28 Jul 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Pipelines |
| Applicant | Department of Irrigation |
| Land area | 143.7 acres (58.2 ha) |
| Forest land | 53.3 acres (21.6 ha) |
| Project cost | ₹1,350 crore |
| Village / locality | Bhuj (M) |
| Taluk / tehsil | Bhuj |
| District | Kachchh |
| State | Gujarat |
| Location from | Site area on record |
| Our reference | WID-GJ-13281 |
In context
59 applications in Kachchh since January 2022 are in the same category (Pipelines): 21 approved, 25 filed or under review, and 13 withdrawn, lapsed or rejected. The approved ones took a median of 6 months from filing to approval. At 143.7 acres, this one is larger than 92% of them.
4 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bhuj (M), Bhuj, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Bhuj to Sumrasar BSNL OFC Route — forest land use approved, 2.4 km away
- Catering a new 9325 KVA Power Demand on 66 KV in respect of M/s Salinity… — more information requested, 2.7 km away
- Construction of Approach Road for the Approach Access — forest land use approved, 3.1 km away
- Dinesh Manji Sorathiya — lapsed, 3.8 km away
- Shri Arrun Gopal Chhanga — environmental approval granted, 9 km away
- Shri Karan Ambadan Gadhavi. — cleared for impact study, 9.1 km away
- Laying of Underground Water Pipeline to Roadside Forest of Bhuj Khavada Road — more information requested, 9.5 km away
- Shri Manji Ravji Gorasia — environmental approval granted, 9.5 km away
More from Department of Irrigation in Kachchh
- Providing Irrigation Water Facility and filling various tanks of Khadir Region… — under forest review
- Epc Work for Construction of Pipeline Project From Tappar Dam to Nirona Dam… — more information requested
- EPC works for Pipeline Project from MPS-3 — more information requested
- Diversion of Forest Land for Saran Sarovar Project in Ta: Rapar, Dist: Kutch — under forest review
- Diversion of Forest Land for Saran Sarovar Project in Ta: Rapar, Dist: Kutch… — not approved
- Laying of Under Ground Water Pipeline for the Irrigation Purpose — under wildlife review
13 Department of Irrigation, Gujarat projects in Kachchh
All 42 Department of Irrigation, Gujarat projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.