Project details
| Official title | Proposed laying of 125 mm Dia MDPE UG Gas pipeline parallel on Navagam - Nayka Road to connect Shayona Silicate Industries in taluka Kheda of district Kheda. |
|---|---|
| Status | In-principle approval, conditions pending |
| Status since | 8 Oct 2026 |
| Application filed | 15 Dec 2025 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Pipelines |
| Applicant | Patel Deepak Amrutlal |
| Land area | 1,200 m² |
| Forest land | 1,160 m² |
| Project cost | ₹12 lakh |
| Village / locality | Chalindra |
| Taluk / tehsil | Kheda |
| District | Kheda |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-13793 |
In context
17 applications in Kheda since January 2022 are in the same category (Pipelines): 12 approved, 3 filed or under review, and 2 withdrawn, lapsed or rejected. The approved ones took a median of 11 months from filing to approval. At 0.3 acres, this one is larger than 50% of them.
11 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Chalindra, Kheda, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Greenfield Project of "Grain Based Distillery Plant of 200 KLD by M/s Shukun… — environmental approval granted, 1 km away
- Proposed Specialty Chemicals Manufacturing Plant of M/s. Expede-Tech Research… — environmental approval granted, 1.1 km away
- Proposed Specialty Chemicals Manufacturing Plant of M/s. Expede-Tech Research… — cleared for impact study, 1.1 km away
- Industrial project by M/s. Accent Microcell Limited (Unit – III) — under environmental review, 1.8 km away
- Industrial project by M/s. Accent Microcell Limited (Unit – III) — cleared for impact study, 1.8 km away
- Industrial project by M/s. Accent Microcell Limited (Unit – III) — lapsed, 1.8 km away
- Industrial project by M/s. Accent Microcell Limited (Unit – III) — cleared for impact study, 1.8 km away
- Proposed 125 mm dia MDPE underground natural gas Pipeline originate from GGS -… — more information requested, 3.2 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.