Quick answers
What is this project?
Diversion of Proposed Roadside Protected Forest land of Gandhidham Mundra Road, Mundra to Old Port Road is an approved telecom project in Bhadresar, Mundra, Kachchh, Gujarat. The site covers 4 acres.
Who is building it?
The applicant is Railtel Corporation of India Limited.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 22 Jul 2024), as of 27 Nov 2026.
Where is it?
In Bhadresar, Mundra, Kachchh, Gujarat.
How big is it?
It has a stated cost of ₹50 crore; a site of 4 acres and 4 acres (1.6 ha) of forest land.
When was it filed?
The application was filed on 18 Oct 2023.
Project details
| Official title | Diversion of Proposed Roadside Protected Forest land of Gandhidham Mundra Road, Mundra to Old Port Road in the Kutch District of State of Gujarat |
|---|---|
| Status | Forest land use approved |
| Status since | 22 Jul 2024 |
| Application filed | 18 Oct 2023 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Telecom |
| Applicant | Railtel Corporation of India Limited |
| Land area | 4 acres (1.6 ha) |
| Forest land | 4 acres (1.6 ha) |
| Project cost | ₹50 crore |
| Village / locality | Bhadresar |
| Taluk / tehsil | Mundra |
| District | Kachchh |
| State | Gujarat |
| Location from | Site boundary on record |
| Our reference | WID-GJ-13851 |
In context
46 applications in Kachchh since January 2022 are in the same category (Telecom): 11 approved, 15 filed or under review, and 20 withdrawn, lapsed or rejected. The approved ones took a median of 9 months from filing to approval. At 4 acres, this one is larger than 86% of them.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bhadresar, Mundra, Kachchh, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Industrial project by M/s. Anmol Polymers Private Limited — environmental approval granted, 1.7 km away
- Industrial project by M/s. Anmol Polymers Private Limited — cleared for impact study, 1.7 km away
- Underground LPG Pipeline at Adani Ports & Special Economic Zone Limited… — more information requested, 4.2 km away
- 300 MW (2x150 MW) coal based Thermal Power Plant — initial checks, 6.1 km away
- Jio Digital Fibre Pvt. Ltd. Laying Of OFC Line District Kutch Village Mathak,… — forest land use approved, 6.3 km away
- Diversion of forest area of Vira Village, Ta: Anjar, Dist: Kutch for… — more information requested, 8.5 km away
- Laying Underground 66 KV Power Cable parallel to Roadside Protected forest… — forest land use approved, 10.5 km away
- Shri Zala Himatsinh. — under environmental review, 10.8 km away
More from Railtel Corporation of India Limited in Kachchh
- Diversion of 0.2182 Ha Proposed Roadside Protected Forest land of Mundra to… — more information requested
- IVFRT Work Gandhidham -Kandla Port — more information requested
3 Railtel Corporation of India projects in Kachchh
All 7 Railtel Corporation of India projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.